15919 W SUNBURST ST 91343

Certificate Information: 15919 W SUNBURST ST 91343

Application / Permit
20014-20000-04753
Plan Check / Job No.
B20VN14101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 19' X 20' DETACHED GARAGE AND ADD 19' X 35'-11" TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP.
Permit Issued
Issued on 3/16/2021
Issuing Office
Valley
Current Status
Issued on 3/16/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/10/2020 RAPHAEL ROSAS
Corrections Issued 11/11/2020 RAPHAEL ROSAS
Applicant returned to address corrections 2/5/2021 RAPHAEL ROSAS
Plan Check Approved 2/24/2021 RAPHAEL ROSAS
Building Plans Picked Up 2/26/2021 APPLICANT
Issued 3/16/2021 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 11/19/2020 RIDWAN HARDY
Address approval Cleared 11/25/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/30/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 1/26/2021 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/26/2021 JOHN TRIANTAFYLLOS
Hold Cleared 1/12/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/3/2023 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 3/8/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 3/8/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 3/16/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/4/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 4/4/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 4/4/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/4/2023 Approved RAUL OLAGI
Sewer 4/4/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/11/2023 Approved RAUL OLAGI
ELECTRICAL-Rough 4/11/2023 Approved RAUL OLAGI
Green Building Rough 4/11/2023 Approved RAUL OLAGI
HVAC-Rough 4/11/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 4/11/2023 Partial Approval RAUL OLAGI
Insulation 4/19/2023 Approved RAUL OLAGI
Drywall Nailing 4/25/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 5/2/2023 Approved RAUL OLAGI
Shower Pan 5/2/2023 Approved RAUL OLAGI
Underground Mechanical 5/2/2023 Approved RAUL OLAGI
Final 4/23/2024 Not Ready for Inspection RAUL OLAGI
Green Building Final 4/23/2024 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/23/2024 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 4/23/2024 Not Ready for Inspection RAUL OLAGI