6620 N GENTRY AVE 91606
Certificate Information: 6620 N GENTRY AVE 91606
- Application / Permit
- 20014-20000-04724
- Plan Check / Job No.
- B20VN14006
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 31'-4" X 21'-3" (2) STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) TO EXISTING DETACHED GARAGE
- Permit Issued
- Issued on 7/6/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2020 | SELLA BENYAMIN |
| Corrections Issued | 12/10/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/14/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/16/2020 | APPLICANT |
| Plan Check Approved | 6/15/2021 | SELLA BENYAMIN |
| Issued | 7/6/2021 | APPLICANT |
| CofO in Progress | 1/31/2023 | JOHN HAYES |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 1/11/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/11/2021 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 2/27/2021 | JEREMY CARTER |
| Low Impact Development | Cleared | 4/9/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 6/2/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2021 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 12/1/2021 | Approved | JACK KARGODORIAN |
| Footing/Foundation/Slab | 12/1/2021 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 1/28/2022 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 1/28/2022 | Not Ready for Inspection | MATT KELLERMAN |
| Wood Frame | 1/28/2022 | Partial Approval | MATT KELLERMAN |
| BUILDING-Rough-Frame | 3/4/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2022 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 3/4/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Partial Inspection | MICHAEL TEMPLE |
| BUILDING-Rough-Frame | 5/3/2022 | Corrections Issued | CALEB MEISTER |
| ELECTRICAL-Rough | 5/3/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 5/3/2022 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 5/3/2022 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 5/3/2022 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 5/3/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Rough | 5/5/2022 | Conditional Approval | CALEB MEISTER |
| HVAC-Rough | 5/5/2022 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 5/5/2022 | Approved | CALEB MEISTER |
| Wood Frame | 5/5/2022 | Corrections Issued | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 6/7/2022 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Rough | 6/7/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 6/7/2022 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 6/7/2022 | Approved | JACK KARGODORIAN |
| Wood Frame | 6/7/2022 | Approved | JACK KARGODORIAN |
| Insulation | 6/30/2022 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/30/2022 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 7/15/2022 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/27/2022 | Approved | JOHN HAYES |
| Final | 12/28/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/28/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/28/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/28/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Final | 1/26/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 1/26/2023 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/26/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 1/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 1/31/2023 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 1/31/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/31/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 1/31/2023 | Approved | JOHN HAYES |