8301 N DENSMORE AVE 91343
Certificate Information: 8301 N DENSMORE AVE 91343
- Application / Permit
- 20014-20000-04718
- Plan Check / Job No.
- B20VN13987
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 10'-3" X 13' ADDITION FOR (N) BEDROOM TO (E) SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/5/2021
- Issuing Office
- Current Status
- CofO Issued on 9/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2020 | RAPHAEL ROSAS |
| Corrections Issued | 11/6/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 12/4/2020 | RAPHAEL ROSAS |
| Issued | 1/5/2021 | APPLICANT |
| CofO in Progress | 8/20/2021 | MICHAEL TEMPLE |
| CofO Issued | 9/8/2021 | MICHAEL SMITH |
| Permit Finaled | 9/8/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/16/2020 | CELINA MORENO |
| Sewer availability | Cleared | 11/16/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/20/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 2/3/2021 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/17/2021 | Partial Approval | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/25/2021 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 2/25/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 3/19/2021 | Approved | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 3/19/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 3/25/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 5/3/2021 | Approved | ARTHUR SARGSYAN |
| Final | 5/3/2021 | OK to Issue CofO | ARTHUR SARGSYAN |
| Green Building Final | 5/3/2021 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 5/3/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 5/3/2021 | Approved | ARTHUR SARGSYAN |