5200-5202 N AVENIDA ORIENTE 91356

Certificate Information: 5200-5202 N AVENIDA ORIENTE 91356

Application / Permit
20014-20000-04717
Plan Check / Job No.
B20VN13986
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 1'-7" LF, 6" LF, AND 1'-5" AT WEST SIDE AND BUILD AN IRREGULAR SHAPED 70'0" X 43'-0" TWO STORY SINGLE FAMILLY DWELLING WITH AN ATTACHED TWO CAR GARAGE AND ATTACHED 23'-11" X 20'-9" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) ALL WORK PER ENGINEERING NFPA-13D FIRE SPRINKLERS REQUIRED
Permit Issued
Issued on 10/19/2021
Issuing Office
Current Status
CofO Issued on 1/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/8/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/22/2020 OMID HEDAYAT
Building Plans Picked Up 12/30/2020 APPLICANT
Applicant returned to address corrections 8/4/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 8/10/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 9/17/2021 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 10/19/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 10/19/2021 SEWADA ZADOORAN MILAGARDI
Issued 10/19/2021 APPLICANT
CofO in Progress 12/28/2023 SEAN HAUPT
Permit Finaled 1/29/2024 JOHN JANSON
CofO Issued 1/29/2024 JOHN JANSON
Permit Finaled 1/29/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/5/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 4/5/2021 GABRIEL ROBLES
Construction near power lines Cleared 5/10/2021 RIDWAN HARDY
Construction within easement Cleared 5/10/2021 RIDWAN HARDY
Sewer availability Cleared 5/11/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 5/24/2021 KURT CORRAL
Low Impact Development Cleared 6/30/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 7/1/2021 CARLOS AGUILERA
GPI Written Notices Cleared 9/13/2021 SEWADA ZADOORAN MILAGARDI
Grading Pre-Inspection Cleared 9/13/2021 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Alpine Design And Build; Lic. No.: 948620-B 18700 SHERMAN WAY # 210      RESEDA, CA 91335
Engineer Babapirzadeh,, Ghazal; Lic. No.: C90480 1530 N DETROIT ST APT 109      LOS ANGELES, CA 90046

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/15/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 11/15/2021 Corrections Issued DAVID SANDOVAL
Sewer 11/15/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 11/22/2021 Partial Approval DAVID SANDOVAL
Underground Mechanical 11/22/2021 Partial Approval DAVID SANDOVAL
Deputy Drilled-In Anchors 12/15/2021 Approved DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 12/15/2021 Approved DAVID SANDOVAL
Footing/Foundation/Slab 12/15/2021 Partial Approval DAVID SANDOVAL
Deputy Reinf. Concrete 12/17/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/14/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 2/23/2022 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 4/25/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 4/27/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 5/3/2022 Approved DAVID SANDOVAL
HVAC-Rough 5/9/2022 Corrections Issued DAVID SANDOVAL
HVAC-Rough 5/17/2022 Approved DAVID SANDOVAL
Underground Mechanical 5/17/2022 Approved DAVID SANDOVAL
Deputy Wood Construction 5/24/2022 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/9/2022 Not Ready for Inspection PETER FOLLING
Green Building Rough 6/9/2022 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 6/14/2022 Approved DAVID SANDOVAL
Insulation 7/14/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/14/2022 Approved MORRIS JACKSON
Drywall Nailing 8/16/2022 Approved DAVID SANDOVAL
Green Building Rough 8/16/2022 Approved DAVID SANDOVAL
Shower Pan 9/12/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 10/13/2022 Approved JESUS PINEDA
BUILDING-Rough-Frame 12/18/2023 Approved SEAN HAUPT
Final 12/18/2023 Corrections Issued SEAN HAUPT
Footing/Foundation/Slab 12/18/2023 Approved SEAN HAUPT
Green Building Final 12/18/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 12/18/2023 Approved SEAN HAUPT
Final 12/21/2023 Not Ready for Inspection SEAN HAUPT
Final 12/27/2023 OK to Issue CofO SEAN HAUPT