19039 W VANOWEN ST 91335
Certificate Information: 19039 W VANOWEN ST 91335
- Application / Permit
- 20014-20000-04715
- Plan Check / Job No.
- B20VN13982
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-10" X 17' 8" ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/28/2020
- Issuing Office
- Current Status
- CofO Issued on 6/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | SELLA BENYAMIN |
| Corrections Issued | 11/10/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 11/12/2020 | APPLICANT |
| Plan Check Approved | 12/17/2020 | SELLA BENYAMIN |
| Issued | 12/28/2020 | APPLICANT |
| CofO in Progress | 6/9/2021 | DAVID SANDOVAL |
| Permit Finaled | 6/12/2021 | MICHAEL SMITH |
| CofO Issued | 6/12/2021 | MICHAEL SMITH |
| Permit Finaled | 6/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/4/2020 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/11/2020 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/5/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Pre-Inspection | 1/5/2021 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 1/8/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/22/2021 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2021 | Approved | VINCENT HANLEY |
| Wood Frame | 1/22/2021 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/5/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 2/5/2021 | Approved | VINCENT HANLEY |
| Insulation | 2/5/2021 | Approved | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 2/5/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/10/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/1/2021 | Partial Inspection | CHRISTOPHER DELLEFIELD |
| Final | 5/17/2021 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 5/17/2021 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/17/2021 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/17/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 6/8/2021 | Approved | DAVID SANDOVAL |
| Final | 6/8/2021 | OK to Issue CofO | DAVID SANDOVAL |
| HVAC-Final | 6/8/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 6/8/2021 | Approved | DAVID SANDOVAL |