6448 N BAKMAN AVE 91606

Certificate Information: 6448 N BAKMAN AVE 91606

Application / Permit
20014-20000-04702
Plan Check / Job No.
B20VN13956
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
DEMO 19'-8"X 11'-11" ATTACHED GARAGE AND 34'-9" X 18' IRREGULAR SHAPE ADDITION TO (E) SFD TO CREATE 2 CAR ATTACHED GARAGE WITH ATTACHED RECREATION ROOM. - 1 OF 2. ALL WORK PER ENGINEER.
Permit Issued
Issued on 6/18/2021
Issuing Office
Current Status
Issued on 6/18/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/26/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 PARISA ZAHABI
Corrections Issued 11/21/2020 PARISA ZAHABI
Quality Review Completed 12/17/2020 OMID HEDAYAT
Applicant returned to address corrections 1/5/2021 PARISA ZAHABI
Applicant returned to address corrections 5/21/2021 PARISA ZAHABI
Plan Check Approved 6/1/2021 PARISA ZAHABI
Building Plans Picked Up 6/1/2021 APPLICANT
Issued 6/18/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2021 MARKOS PEREZ-BRAN
Sewer availability Cleared 1/8/2021 MARKOS PEREZ-BRAN
Low Impact Development Cleared 4/30/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/21/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/26/2021 Partial Approval ADAM ESCOTO
Footing/Foundation/Slab 8/5/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 10/29/2021 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/29/2021 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/2/2022 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 6/27/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/12/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 7/16/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 7/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Deputy Steel/Welding 8/26/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 2/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/26/2026 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/26/2026 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 2/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 2/26/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 6/2/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 6/2/2026 Approved GAREN HAYRAPETYAN
Insulation 6/2/2026 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 6/2/2026 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 6/2/2026 Approved GAREN HAYRAPETYAN