18101 W KAREN DR 91356
Certificate Information: 18101 W KAREN DR 91356
- Application / Permit
- 20014-20000-04695
- Plan Check / Job No.
- B20VN13918
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'-2" X 37' ADDITION TO REAR OF SINGLE FAMILY DWELLING TO ENLARGE EXISTING BEDROOMS AND ADD OPEN TRELLIS
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Current Status
- CofO Issued on 7/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | SELLA BENYAMIN |
| Corrections Issued | 11/10/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 11/13/2020 | APPLICANT |
| Plan Check Approved | 12/28/2020 | SELLA BENYAMIN |
| Issued | 1/29/2021 | APPLICANT |
| CofO in Progress | 6/14/2022 | DAVID SANDOVAL |
| CofO Issued | 7/18/2022 | MICHAEL SMITH |
| Permit Finaled | 7/18/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/12/2020 | SELLA BENYAMIN |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shamsrad,, Shima; Lic. No.: C88470 | 12300 MONTECITO RD 47 SEAL BEACH, CA 90740 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/8/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/15/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/27/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2021 | Partial Approval | HENRY KIM |
| Insulation | 5/6/2021 | Partial Approval | HENRY KIM |
| BUILDING-Rough-Frame | 5/21/2021 | Partial Inspection | RONALD COWAN |
| Green Building Rough | 5/21/2021 | Not Ready for Inspection | RONALD COWAN |
| BUILDING-Rough-Frame | 5/27/2021 | Partial Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/14/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/14/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Rough | 6/14/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 6/14/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Insulation | 6/14/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 6/14/2021 | Corrections Issued | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/16/2021 | Corrections Issued | DAVID SANDOVAL |
| Insulation | 6/16/2021 | Partial Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 6/16/2021 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/25/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 6/25/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/25/2021 | Approved | DAVID SANDOVAL |
| Insulation | 6/25/2021 | Approved | DAVID SANDOVAL |
| PLUMBING-Rough | 6/25/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 7/8/2021 | No Access for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 7/14/2021 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Rough | 7/14/2021 | Approved | PETER FOLLING |
| Final | 8/30/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 8/30/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2021 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 8/30/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 10/18/2021 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 10/18/2021 | Approved | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 10/18/2021 | SGSOV Not Ready | DAVID SANDOVAL |
| Smoke Detectors | 10/18/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 10/27/2021 | Corrections Issued | PETER FOLLING |
| Grading Pre-Inspection | 10/27/2021 | Not Ready for Inspection | PETER FOLLING |
| SGSOV-Seismic Gas S/O Valve | 10/27/2021 | SGSOV Approved | PETER FOLLING |
| Smoke Detectors | 10/27/2021 | Approved | PETER FOLLING |
| Final | 4/14/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 6/13/2022 | OK to Issue CofO | DAVID SANDOVAL |