9452 N OBECK AVE 91331

Certificate Information: 9452 N OBECK AVE 91331

Application / Permit
20014-20000-04664
Plan Check / Job No.
B20VN13857
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
1ST AND 2ND FLOOR ADDITION TO THE (E) DETACHED GARAGE FOR A 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/15/2021
Issuing Office
Valley
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 11/19/2020 COLIN LOREDO
Corrections Issued 11/25/2020 COLIN LOREDO
Quality Review Completed 12/17/2020 OMID HEDAYAT
Building Plans Picked Up 12/17/2020 APPLICANT
Plan Check Approved 10/25/2021 COLIN LOREDO
Issued 11/15/2021 APPLICANT
CofO in Progress 3/21/2023 GREGG CUMMINGS
Permit Finaled 3/29/2023 MICHAEL SMITH
CofO Issued 3/29/2023 MICHAEL SMITH
Permit Finaled 3/29/2023 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 5/8/2021 ANDRES COVARRUBIAS
Address approval Cleared 5/11/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 5/11/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 5/11/2021 GABRIEL ROBLES
Sewer availability Cleared 5/11/2021 GABRIEL ROBLES
Construction near power lines Cleared 6/22/2021 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2022 Approved GREGG CUMMINGS
Deputy Drilled-In Anchors 4/14/2022 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 4/29/2022 Approved JENNIFER RABUCHIN
PLUMBING-Rough 4/29/2022 Partial Approval JENNIFER RABUCHIN
Deputy Reinf. Concrete 5/3/2022 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval GREGG CUMMINGS
Deputy Wood Construction 7/18/2022 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 9/1/2022 Corrections Issued ALAN MORELOS
ELECTRICAL-Rough 9/1/2022 Approved ALAN MORELOS
Green Building Rough 9/1/2022 Not Ready for Inspection ALAN MORELOS
HVAC-Rough 9/1/2022 Approved ALAN MORELOS
PLUMBING-Rough 9/1/2022 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 10/13/2022 Approved WILLIAM WREN
Insulation 10/27/2022 Corrections Issued WILLIAM WREN
Insulation 11/3/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 11/23/2022 Approved GREGG CUMMINGS
Drywall Nailing 11/23/2022 Approved GREGG CUMMINGS
Green Building Rough 11/23/2022 Approved GREGG CUMMINGS
Shower Pan 11/23/2022 Approved GREGG CUMMINGS
Interior/Exterior Lathing 12/8/2022 Approved CHRISTOPHER DELLEFIELD
Final 3/14/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 3/14/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/14/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 3/14/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Final 3/20/2023 Approved GREGG CUMMINGS
Final 3/20/2023 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 3/20/2023 Approved GREGG CUMMINGS
PLUMBING-Final 3/20/2023 Approved GREGG CUMMINGS
Smoke Detectors 3/20/2023 Approved GREGG CUMMINGS