9452 N OBECK AVE 91331
Certificate Information: 9452 N OBECK AVE 91331
- Application / Permit
- 20014-20000-04664
- Plan Check / Job No.
- B20VN13857
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 1ST AND 2ND FLOOR ADDITION TO THE (E) DETACHED GARAGE FOR A 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 11/15/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | COLIN LOREDO |
| Corrections Issued | 11/25/2020 | COLIN LOREDO |
| Quality Review Completed | 12/17/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/17/2020 | APPLICANT |
| Plan Check Approved | 10/25/2021 | COLIN LOREDO |
| Issued | 11/15/2021 | APPLICANT |
| CofO in Progress | 3/21/2023 | GREGG CUMMINGS |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
| CofO Issued | 3/29/2023 | MICHAEL SMITH |
| Permit Finaled | 3/29/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 5/8/2021 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 6/22/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2022 | Approved | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 4/14/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 4/29/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 4/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Reinf. Concrete | 5/3/2022 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Partial Approval | GREGG CUMMINGS |
| Deputy Wood Construction | 7/18/2022 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 9/1/2022 | Corrections Issued | ALAN MORELOS |
| ELECTRICAL-Rough | 9/1/2022 | Approved | ALAN MORELOS |
| Green Building Rough | 9/1/2022 | Not Ready for Inspection | ALAN MORELOS |
| HVAC-Rough | 9/1/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 9/1/2022 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/13/2022 | Approved | WILLIAM WREN |
| Insulation | 10/27/2022 | Corrections Issued | WILLIAM WREN |
| Insulation | 11/3/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 11/23/2022 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 11/23/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 11/23/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 11/23/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/14/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/14/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2023 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 3/14/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 3/20/2023 | Approved | GREGG CUMMINGS |
| Final | 3/20/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 3/20/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 3/20/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 3/20/2023 | Approved | GREGG CUMMINGS |