11521 N SEMINOLE CIR 91326
Certificate Information: 11521 N SEMINOLE CIR 91326
- Application / Permit
- 20014-20000-04588
- Plan Check / Job No.
- B20VN13662
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW 58' X 23'-1" ENCLOSED PATIO COVER
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | SELLA BENYAMIN |
| Corrections Issued | 11/24/2020 | SELLA BENYAMIN |
| Quality Review Completed | 12/2/2020 | STEVEN KIM |
| Building Plans Picked Up | 12/2/2020 | APPLICANT |
| Applicant returned to address corrections | 4/30/2021 | SELLA BENYAMIN |
| Plan Check Approved | 6/11/2021 | SELLA BENYAMIN |
| Issued | 4/26/2022 | APPLICANT |
| CofO in Progress | 7/26/2023 | DAVID SCANTLIN |
| Permit Finaled | 9/12/2023 | JOHN JANSON |
| CofO Issued | 9/12/2023 | JOHN JANSON |
| Permit Finaled | 9/12/2023 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/10/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 2/10/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 2/10/2021 | JOHN TRIANTAFYLLOS |
| BHO/Hillside ordinance | Cleared | 2/10/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 4/16/2021 | ORVAL HERNANDEZ-MARCI |
| BHO/Hillside ordinance | Cleared | 5/4/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 5/4/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 5/4/2021 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 5/4/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 5/11/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/15/2022 | Approved | DAVID SCANTLIN |
| Pre-Inspection | 1/24/2023 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/4/2023 | Partial Approval | DAVID SCANTLIN |
| Footing/Foundation/Slab | 4/11/2023 | Approved | DAVID SCANTLIN |
| METHANE-Barrier | 4/11/2023 | Approved | DAVID SCANTLIN |
| METHANE-Subgrade | 4/11/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 5/1/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/1/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 5/23/2023 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/23/2023 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 5/25/2023 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | DAVID SCANTLIN |
| Final | 7/25/2023 | OK to Issue CofO | DAVID SCANTLIN |
| Green Building Final | 7/25/2023 | Approved | DAVID SCANTLIN |
| Green Building Rough | 7/25/2023 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/25/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 7/25/2023 | Approved | DAVID SCANTLIN |