5230 N MELVIN AVE 91356
Certificate Information: 5230 N MELVIN AVE 91356
- Application / Permit
- 20014-20000-04577
- Plan Check / Job No.
- B20VN13651
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL & ADDITION TO MAKE AN IRREGULAR SHAPED 47'6"X93'6" 2-STORY SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE AND A TRELLIS ON THE 1ST FLOOR & A TRELLIS ON THE 2ND FLOOR. NFPA 13 D FIRE SPRINKLERS REQUIRED THROGHOUT
- Permit Issued
- Issued on 4/9/2021
- Issuing Office
- Current Status
- CofO Issued on 11/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | MARVEL DELACRUZ |
| Corrections Issued | 11/18/2020 | MARVEL DELACRUZ |
| Quality Review Completed | 11/20/2020 | STEVEN KIM |
| Building Plans Picked Up | 11/20/2020 | APPLICANT |
| Applicant returned to address corrections | 2/5/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 3/26/2021 | MARVEL DELACRUZ |
| Issued | 4/9/2021 | APPLICANT |
| CofO in Progress | 11/7/2023 | SEAN HAUPT |
| CofO Issued | 11/22/2023 | JOHN JANSON |
| Permit Finaled | 11/22/2023 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 12/3/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 12/3/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 12/3/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 12/3/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 12/3/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2020 | GUILLERMO PETRA |
| Permit | Cleared | 12/3/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/3/2020 | GUILLERMO PETRA |
| Distance to fire station | Cleared | 12/18/2020 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 12/18/2020 | ROBERT DUFF |
| Low Impact Development | Cleared | 3/5/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/5/2021 | ADRIAN CASTRO |
| Green Code | Cleared | 3/26/2021 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Abrahamian,, Zaven; Lic. No.: C41672 | 237 S LAMER ST BURBANK, CA 91506 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/21/2021 | Conditional Approval | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/26/2021 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 4/27/2021 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 5/14/2021 | Partial Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 5/14/2021 | Partial Inspection | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Inspection | DAVID SANDOVAL |
| Deputy Steel/Welding | 6/7/2021 | Conditional Approval | DAVID SANDOVAL |
| Deputy Wood Construction | 7/7/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2021 | Partial Approval | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Partial Approval | DAVID SANDOVAL |
| HVAC-Rough | 10/28/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 10/28/2021 | Approved | DAVID SANDOVAL |
| ELECTRICAL-Rough | 12/6/2021 | Approved | DAVID SANDOVAL |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2021 | Approved | DAVID SANDOVAL |
| HVAC-Rough | 12/6/2021 | Approved | DAVID SANDOVAL |
| Green Building Rough | 12/22/2021 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 12/22/2021 | Partial Approval | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 1/3/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 1/3/2022 | Approved | DAVID SANDOVAL |
| Insulation | 1/3/2022 | Approved | DAVID SANDOVAL |
| Verify Sprinkler Sign Off | 1/3/2022 | Approved | DAVID SANDOVAL |
| Drywall Nailing | 1/12/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 1/19/2022 | Approved | JUSTIN HAWLEY |
| Sewer | 12/22/2022 | Approved | DAVID SANDOVAL |
| Pre-Inspection | 9/7/2023 | Partial Inspection | SEAN WIRCH |
| Service/Power Release | 9/25/2023 | Approved | PETER FOLLING |
| Final | 10/11/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 10/11/2023 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/11/2023 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 10/11/2023 | Not Ready for Inspection | SEAN HAUPT |
| Final | 10/19/2023 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 10/19/2023 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 10/19/2023 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 10/19/2023 | Approved | SEAN HAUPT |
| Final | 11/6/2023 | OK to Issue CofO | SEAN HAUPT |