14050 W BURTON ST 91402
Certificate Information: 14050 W BURTON ST 91402
- Application / Permit
- 20014-20000-04571
- Plan Check / Job No.
- B20VN13641
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 9' X 21' 7" ADDITION TO FRONT & 3' 8" X 22' 2" ADDITION TO REAR OF (E) DETACHED GARAGE AND CONVERT TO ADU. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 4/19/2021
- Issuing Office
- Current Status
- CofO Issued on 2/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 3/30/2020 | APPLICANT |
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 11/26/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 3/8/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 3/16/2021 | GURUNATH NESARAJAH |
| Issued | 4/19/2021 | APPLICANT |
| CofO in Progress | 2/7/2023 | GREGG CUMMINGS |
| CofO Issued | 2/17/2023 | MICHAEL SMITH |
| Permit Finaled | 2/17/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/18/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/22/2020 | ADRIAN CASTRO |
| Construction near power lines | Cleared | 2/16/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/2/2021 | Conditional Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 1/13/2022 | Partial Approval | GREGG CUMMINGS |
| Sewer | 1/13/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 1/18/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 1/18/2022 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 1/18/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/14/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/14/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Gas Test | 3/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 3/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 3/14/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 3/14/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/22/2022 | Approved | GREGG CUMMINGS |
| Green Building Rough | 3/22/2022 | Approved | GREGG CUMMINGS |
| Insulation | 4/5/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 4/5/2022 | Approved | WILLIAM WREN |
| Drywall Nailing | 4/22/2022 | Approved | GREGG CUMMINGS |
| Gas Test | 4/22/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/22/2022 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 4/22/2022 | Corrections Issued | GREGG CUMMINGS |
| Shower Pan | 5/31/2022 | Approved | WILLIAM WREN |
| Gas Test | 8/2/2022 | Approved | WILLIAM WREN |
| Underground Mechanical | 8/2/2022 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Final | 10/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/5/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 10/5/2022 | Approved | GREGG CUMMINGS |
| HVAC-Final | 10/5/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 10/5/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/5/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 10/18/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/18/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Final | 10/18/2022 | Approved | GREGG CUMMINGS |
| Final | 2/3/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/6/2023 | Approved | GREGG CUMMINGS |
| Final | 2/6/2023 | OK to Issue CofO | GREGG CUMMINGS |