9736 N LUBAO AVE 91311
Certificate Information: 9736 N LUBAO AVE 91311
- Application / Permit
- 20014-20000-04558
- Plan Check / Job No.
- B20VN13615
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 9'10-1/8" X 13'6" DINING ROOM ADDITION
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- CofO Issued on 7/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/30/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 1/27/2021 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 4/7/2021 | PETER MOSESIAN |
| Plan Check Approved | 4/22/2021 | PETER MOSESIAN |
| Issued | 4/29/2021 | APPLICANT |
| CofO in Progress | 7/20/2021 | JEFFREY PARD |
| CofO Issued | 7/20/2021 | JOHN JANSON |
| Permit Finaled | 7/20/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/14/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 4/14/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 5/18/2021 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 5/18/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 5/18/2021 | Not Ready for Inspection | JEFFREY PARD |
| Wood Frame | 5/18/2021 | Approved | JEFFREY PARD |
| Insulation | 6/1/2021 | Approved | JUSTIN HAWLEY |
| Drywall Nailing | 6/7/2021 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/19/2021 | Approved | JEFFREY PARD |
| Final | 7/19/2021 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 7/19/2021 | Approved | JEFFREY PARD |
| Green Building Rough | 7/19/2021 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 7/19/2021 | SGSOV Approved | JEFFREY PARD |
| Smoke Detectors | 7/19/2021 | Approved | JEFFREY PARD |