7837 N NEVADA AVE 91304

Certificate Information: 7837 N NEVADA AVE 91304

Application / Permit
20014-20000-04557
Plan Check / Job No.
B20VN13610
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
30'-3" X 28'-3" IRREGULAR SHAPED ADDITION OF NEW BEDROOM, LIVING ROOM AND TRELLIS
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 11/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 SELLA BENYAMIN
Corrections Issued 11/2/2020 SELLA BENYAMIN
Building Plans Picked Up 11/2/2020 APPLICANT
Plan Check Approved 12/3/2020 SELLA BENYAMIN
Issued 2/25/2021 APPLICANT
CofO in Progress 11/5/2021 DAVID STEPANYAN
Permit Finaled 11/9/2021 JOHN JANSON
CofO Issued 11/9/2021 JOHN JANSON
Permit Finaled 11/9/2021 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/18/2020 ADRIAN CASTRO
Sewer availability Cleared 11/18/2020 ADRIAN CASTRO

Contact Information

Contractor Davidson Development Inc; Lic. No.: 1010509-B 655 MARTHA DRIVE      NEWBURY PARK, CA 91320

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/5/2021 Corrections Issued DAVID STEPANYAN
BUILDING-Rough-Frame 3/17/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 3/17/2021 Not Ready for Inspection DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval DAVID STEPANYAN
Insulation 3/22/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 3/31/2021 Partial Approval DAVID STEPANYAN
Green Building Rough 3/31/2021 Not Ready for Inspection DAVID STEPANYAN
BUILDING-Rough-Frame 4/19/2021 Approved DAVID STEPANYAN
ELECTRICAL-Rough 4/19/2021 Approved DAVID STEPANYAN
Green Building Rough 4/19/2021 Approved DAVID STEPANYAN
HVAC-Rough 4/19/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 4/19/2021 Approved DAVID STEPANYAN
Shower Pan 4/19/2021 Approved DAVID STEPANYAN
Insulation 4/20/2021 Approved DAVID STEPANYAN
Drywall Nailing 4/27/2021 Corrections Issued JUSTIN HAWLEY
Interior/Exterior Lathing 4/27/2021 Partial Approval JUSTIN HAWLEY
Pre-Inspection 4/27/2021 Partial Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 5/3/2021 Partial Approval STEPHANIE SWANSON
Pre-Inspection 5/3/2021 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 7/22/2021 Approved DAVID STEPANYAN
Final 7/22/2021 Corrections Issued DAVID STEPANYAN
Footing/Foundation/Slab 7/22/2021 Approved DAVID STEPANYAN
Green Building Final 7/22/2021 Approved DAVID STEPANYAN
HVAC-Final 7/22/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 7/22/2021 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 7/22/2021 Approved DAVID STEPANYAN
Final 11/4/2021 OK to Issue CofO DAVID STEPANYAN
PLUMBING-Final 11/4/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 11/4/2021 SGSOV Approved DAVID STEPANYAN