531 N GOWER ST 90004
Certificate Information: 531 N GOWER ST 90004
- Application / Permit
- 20014-20000-04556
- Plan Check / Job No.
- B20VN13602
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- 23'-2" X 17'-2" ADDITION TO THE (E) DETACHED GARAGE.
- Permit Issued
- Issued on 2/2/2021
- Issuing Office
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | SERGIO MUNIZ |
| Corrections Issued | 10/30/2020 | SERGIO MUNIZ |
| Plan Check Approved | 12/7/2020 | SERGIO MUNIZ |
| Issued | 2/2/2021 | APPLICANT |
| CofO in Progress | 6/17/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
| CofO Issued | 7/2/2021 | DEROLD HAUFF |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 12/7/2020 | RENZ SORIANO |
Contact Information
| Contractor | Root Construction; Lic. No.: 872584-B | 17216 SATICOY ST #180 VAN NUYS, CA 91406 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/10/2021 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 2/25/2021 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 4/1/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Pre-Inspection | 5/3/2021 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 5/21/2021 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/1/2021 | Partial Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 6/1/2021 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 6/1/2021 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 6/9/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/9/2021 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 6/9/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/16/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 6/16/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 6/16/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 6/16/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Final | 6/16/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 6/16/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/16/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/16/2021 | Approved | CHRIS CHRISTENSEN |