531 N GOWER ST 90004

Certificate Information: 531 N GOWER ST 90004

Application / Permit
20014-20000-04556
Plan Check / Job No.
B20VN13602
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
23'-2" X 17'-2" ADDITION TO THE (E) DETACHED GARAGE.
Permit Issued
Issued on 2/2/2021
Issuing Office
Current Status
CofO Issued on 7/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 SERGIO MUNIZ
Corrections Issued 10/30/2020 SERGIO MUNIZ
Plan Check Approved 12/7/2020 SERGIO MUNIZ
Issued 2/2/2021 APPLICANT
CofO in Progress 6/17/2021 CHRIS CHRISTENSEN
Permit Finaled 7/2/2021 DEROLD HAUFF
CofO Issued 7/2/2021 DEROLD HAUFF
Permit Finaled 7/2/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/7/2020 RENZ SORIANO
Roof/Waste drainage to street Cleared 12/7/2020 RENZ SORIANO

Contact Information

Contractor Root Construction; Lic. No.: 872584-B 17216 SATICOY ST #180      VAN NUYS, CA 91406
Engineer Garcia,, Lionel Jesus; Lic. No.: S4653 24702 NARBONNE AVE      LOMITA, CA 90717

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/10/2021 Approved CHRIS CHRISTENSEN
Pre-Inspection 2/25/2021 Approved CHRIS CHRISTENSEN
Pre-Inspection 4/1/2021 Corrections Issued CHRIS CHRISTENSEN
Pre-Inspection 5/3/2021 Partial Approval JOSEPH MCGARRY
Pre-Inspection 5/21/2021 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/1/2021 Partial Approval JOSEPH MCGARRY
METHANE-Barrier 6/1/2021 Approved JOSEPH MCGARRY
METHANE-Subgrade 6/1/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 6/9/2021 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 6/9/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 6/9/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/16/2021 Approved CHRIS CHRISTENSEN
Final 6/16/2021 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 6/16/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 6/16/2021 Approved CHRIS CHRISTENSEN
METHANE-Final 6/16/2021 Approved CHRIS CHRISTENSEN
METHANE-Rough 6/16/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/16/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/16/2021 Approved CHRIS CHRISTENSEN