2563 S AMHERST AVE 90064

Certificate Information: 2563 S AMHERST AVE 90064

Application / Permit
20014-20000-04546
Plan Check / Job No.
B20VN13572
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) & ADD (N) STORAGE ROOM (12'-1" X 3'-1") PER ENG'R DESIGN
Permit Issued
Issued on 3/9/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 NILOOFAR MEHRAIN
Corrections Issued 11/4/2020 NILOOFAR MEHRAIN
Plan Check Approved 1/13/2021 NILOOFAR MEHRAIN
Issued 3/9/2021 APPLICANT
Building Plans Picked Up 3/11/2021 APPLICANT
CofO in Progress 8/22/2022 JOHNNY MIRANDA
Permit Finaled 8/23/2022 DANIEL ORRANTE
CofO Issued 8/23/2022 DANIEL ORRANTE
Permit Finaled 8/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Specific Plan Cleared 11/19/2020 DYLAN SITTIG
ZI Cleared 11/19/2020 DYLAN SITTIG
Hydrant and Access approval Cleared 12/4/2020 GILBERT URREA
Address approval Cleared 12/8/2020 NIKTA MOUSAVI
Eng Process Fee Ord 176,300 Cleared 12/16/2020 NIKTA MOUSAVI
Sewer availability Cleared 12/17/2020 NIKTA MOUSAVI
Roof/Waste drainage to street Cleared 12/18/2020 NIKTA MOUSAVI

Contact Information

Contractor Polymath Development Group Inc; Lic. No.: 1069728-B 7341 AMESTOY AVENUE      VAN NUYS, CA 91406

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/15/2021 Partial Inspection KENNETH NAGLE
PLUMBING-Rough 6/16/2021 Partial Inspection JACK MATTILLO
Shower Pan 6/25/2021 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/9/2021 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/23/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 8/23/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Special/Order Compliance 8/23/2021 Corrections Issued OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 9/16/2021 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 9/20/2021 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 9/20/2021 No Access for Inspection KENNETH NAGLE
Green Building Rough 9/20/2021 No Access for Inspection KENNETH NAGLE
PLUMBING-Rough 9/20/2021 No Access for Inspection KENNETH NAGLE
Wood Frame 9/20/2021 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 9/21/2021 Approved KENNETH NAGLE
Deputy Drilled-In Anchors 10/4/2021 No Access for Inspection KENNETH NAGLE
Footing/Foundation/Slab 10/5/2021 Approved KENNETH NAGLE
Green Building Final 10/20/2021 Not Ready for Inspection JOHNNY MIRANDA
Insulation 10/20/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 10/29/2021 Approved JOHNNY MIRANDA
Drywall Nailing 10/29/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Approved JOHNNY MIRANDA
Green Building Rough 10/29/2021 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/29/2021 Partial Approval JOHNNY MIRANDA
Shower Pan 10/29/2021 Corrections Issued JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Approved JOHNNY MIRANDA
Shower Pan 12/20/2021 Approved JOHNNY MIRANDA
Final 8/15/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 8/15/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/15/2022 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 8/15/2022 Approved JOHNNY MIRANDA
Final 8/19/2022 Partial Approval JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Approved JOHNNY MIRANDA