GROUND FLOOR ADDITION OF 2 STORY WITH LOFT AND STORAGE (17'-2"X16'-9")
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
Issued on 2/9/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/3/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 MOHAMMAD ESMAILI
Corrections Issued 12/5/2020 MOHAMMAD ESMAILI
Quality Review Completed 12/11/2020 OMID HEDAYAT
Building Plans Picked Up 12/16/2020 APPLICANT
Plan Check Approved 11/1/2021 MOHAMMAD ESMAILI
Issued 2/9/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/21/2021 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 1/27/2021 JOHN TRIANTAFYLLOS
ZI Cleared 3/1/2021 MIGUEL GAMBOA

Contact Information

Contractor My Design Remodeling Inc; Lic. No.: 982016-B 5744 WILHELMINA AVENUE      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
MORRIS JACKSON, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/18/2022 Not Ready for Inspection SEAN HAUPT
Footing/Foundation/Slab 2/18/2022 Corrections Issued SEAN HAUPT
Excavation/Setback/Form/Re-Bar 2/28/2022 Not Ready for Inspection SEAN HAUPT
Excavation/Setback/Form/Re-Bar 3/4/2022 Approved SEAN HAUPT
Footing/Foundation/Slab 3/4/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Partial Approval SEAN HAUPT
PLUMBING-Rough 3/15/2022 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 6/6/2022 Approved SEAN HAUPT
ELECTRICAL-Rough 6/6/2022 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Approved SEAN HAUPT
Green Building Rough 6/6/2022 Approved SEAN HAUPT
MERV13>=Rough 6/6/2022 Approved SEAN HAUPT
PLUMBING-Rough 6/6/2022 Approved SEAN HAUPT
Green Building Rough 6/27/2022 Approved DAVID SANDOVAL
HVAC-Rough 6/27/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 6/27/2022 Partial Approval DAVID SANDOVAL
Insulation 7/6/2022 Approved SEAN HAUPT
Drywall Nailing 7/14/2022 Approved SEAN HAUPT
Shower Pan 7/14/2022 Not Ready for Inspection SEAN HAUPT
Shower Pan 8/3/2022 Corrections Issued JUSTIN HAWLEY
Shower Pan 8/4/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 8/22/2022 Approved SEAN HAUPT
Final 4/11/2023 Corrections Issued SEAN HAUPT
Green Building Final 4/11/2023 Not Ready for Inspection SEAN HAUPT
MERV13>=Final 4/11/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Approved SEAN HAUPT
Smoke Detectors 4/11/2023 Approved SEAN HAUPT