6540 N VALLEY CIRCLE BLVD 91307
Certificate Information: 6540 N VALLEY CIRCLE BLVD 91307
- Application / Permit
- 20014-20000-04543
- Plan Check / Job No.
- B20VN13548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21'-5" X 22'-9" ADDITION TO THE (E) SINGLE FAMILY DWELLING AND REMODEL.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | SERGIO MUNIZ |
| Corrections Issued | 10/30/2020 | SERGIO MUNIZ |
| Plan Check Approved | 3/15/2021 | SERGIO MUNIZ |
| Building Plans Picked Up | 3/18/2021 | APPLICANT |
| Issued | 5/24/2021 | APPLICANT |
| CofO in Progress | 10/31/2021 | TROY SANDERS |
| Permit Finaled | 12/7/2021 | JOHN JANSON |
| CofO Issued | 12/7/2021 | JOHN JANSON |
| Permit Finaled | 12/7/2021 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 3/1/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 5/14/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Dotz Inc; Lic. No.: 1033830-B | 17321 MURPHY AVENUE #240 IRVINE, CA 92614 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 5/26/2021 | Approved | TROY SANDERS |
| Deputy Reinf. Concrete | 5/28/2021 | Approved | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 6/16/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 6/16/2021 | Approved | TROY SANDERS |
| Sewer | 6/16/2021 | Approved | TROY SANDERS |
| Insulation | 6/22/2021 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 6/22/2021 | Not Ready for Inspection | TROY SANDERS |
| Shower Pan | 6/22/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 6/28/2021 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 6/30/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 6/30/2021 | Not Ready for Inspection | TROY SANDERS |
| BUILDING-Rough-Frame | 8/3/2021 | Approved | TROY SANDERS |
| Green Building Rough | 8/3/2021 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/3/2021 | Partial Approval | TROY SANDERS |
| Insulation | 8/6/2021 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 8/11/2021 | Approved | STEPHANIE SWANSON |
| Final | 8/11/2021 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/11/2021 | Partial Inspection | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/17/2021 | Approved | STEPHANIE SWANSON |
| Final | 10/29/2021 | OK to Issue CofO | TROY SANDERS |
| Footing/Foundation/Slab | 10/29/2021 | Approved | TROY SANDERS |
| Green Building Final | 10/29/2021 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 10/29/2021 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 10/29/2021 | Approved | TROY SANDERS |