4327 N GRIMES PL 91316

Certificate Information: 4327 N GRIMES PL 91316

Application / Permit
20014-20000-04541
Plan Check / Job No.
B20VN13541
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 13' X 29' ADDITION FOR (N) BEDROOM AND BATHROOM TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/21/2020
Issuing Office
Current Status
CofO Issued on 7/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2020 APPLICANT
Assigned to Plan Check Engineer 10/28/2020 RAPHAEL ROSAS
Corrections Issued 10/29/2020 RAPHAEL ROSAS
Plan Check Approved 12/1/2020 RAPHAEL ROSAS
Issued 12/21/2020 APPLICANT
CofO in Progress 7/6/2021 DAVID SANDOVAL
Permit Finaled 7/10/2021 MICHAEL SMITH
CofO Issued 7/10/2021 MICHAEL SMITH
Permit Finaled 7/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/16/2020 MANUEL TEJADA
Eng Process Fee Ord 176,300 Cleared 11/23/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 11/23/2020 GABRIEL ROBLES
Sewer availability Cleared 11/23/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/21/2021 Partial Approval DAVID SANDOVAL
Footing/Foundation/Slab 1/27/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 2/26/2021 Corrections Issued DAVID SANDOVAL
ELECTRICAL-Rough 2/26/2021 Corrections Issued DAVID SANDOVAL
Green Building Rough 2/26/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 2/26/2021 Corrections Issued DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Partial Approval DAVID SANDOVAL
HVAC-Rough 3/1/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 3/1/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 3/8/2021 Approved DAVID SANDOVAL
HVAC-Rough 3/8/2021 Approved DAVID SANDOVAL
Interior/Exterior Lathing 3/22/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/12/2021 Not Ready for Inspection DAVID SANDOVAL
Deputy Wood Construction 4/14/2021 Conditional Approval DAVID SANDOVAL
BUILDING-Rough-Frame 4/20/2021 Partial Approval RONALD COWAN
Green Building Rough 4/20/2021 Approved RONALD COWAN
Insulation 4/20/2021 Approved RONALD COWAN
Drywall Nailing 4/27/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 4/27/2021 Not Ready for Inspection RYAN SALAZAR
Pre-Inspection 4/27/2021 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 5/6/2021 Approved DAVID SANDOVAL
Shower Pan 5/6/2021 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/25/2021 Approved DAVID SANDOVAL
Final 6/25/2021 Partial Inspection DAVID SANDOVAL
Green Building Final 6/25/2021 Not Ready for Inspection DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 6/25/2021 SGSOV Approved DAVID SANDOVAL
Smoke Detectors 6/25/2021 Approved DAVID SANDOVAL
ELECTRICAL-Final 7/2/2021 Approved DAVID SANDOVAL
Final 7/2/2021 OK to Issue CofO DAVID SANDOVAL
Green Building Final 7/2/2021 Approved DAVID SANDOVAL
HVAC-Final 7/2/2021 Approved DAVID SANDOVAL
PLUMBING-Final 7/2/2021 Approved DAVID SANDOVAL