4836 N AGNES AVE 91607
Certificate Information: 4836 N AGNES AVE 91607
- Application / Permit
- 20014-20000-04525
- Plan Check / Job No.
- B20VN13495
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTEND (E) MASTER CLOSET & FAMILY ROOM ON FIRST FLOOR & ADD (2) BEDROOMS/(2) FULL BATHROOMS & SITTING AREA ON 2ND FLOOR TO (E) 1-STORY SFD WITH ATTACHED GARAGE; INTERIOR REMODEL; DEMO (E) COV'D PATIO & ADD (N) PATIO (17'-6" X 7') AT REAR OF SFD
- Permit Issued
- Issued on 4/7/2021
- Issuing Office
- Current Status
- CofO Issued on 8/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/27/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 10/27/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 1/28/2021 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/9/2021 | NILOOFAR MEHRAIN |
| Issued | 4/7/2021 | APPLICANT |
| Building Plans Picked Up | 4/12/2021 | APPLICANT |
| CofO in Progress | 4/27/2022 | ARAM AVEDISIAN |
| Permit Finaled | 8/6/2022 | DEROLD HAUFF |
| CofO Issued | 8/6/2022 | DEROLD HAUFF |
| Permit Finaled | 8/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/16/2020 | JOHN TRIANTAFYLLOS |
| Specific Plan | Cleared | 1/7/2021 | ANDREW JORGENSEN |
| ZI | Cleared | 1/7/2021 | ANDREW JORGENSEN |
| ZI | Cleared | 1/7/2021 | ANDREW JORGENSEN |
| Miscellaneous | Cleared | 1/13/2021 | DANG NGUYEN |
| Low Impact Development | Cleared | 2/9/2021 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/16/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Bellagio Design Build Corporation; Lic. No.: 935571-B | 19336 CALVERT STREET TARZANA, CA 91335 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/9/2021 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 4/22/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/29/2021 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 4/29/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 4/29/2021 | Not Ready for Inspection | MATTHEW NELSON |
| BUILDING-Rough-Frame | 5/10/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Deputy Wood Construction | 5/21/2021 | Conditional Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 6/1/2021 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 6/1/2021 | Partial Inspection | THOMAS FINNILA |
| Wood Frame | 6/1/2021 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/11/2021 | Corrections Issued | THOMAS FINNILA |
| HVAC-Rough | 6/11/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/11/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/17/2021 | Approved | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 6/17/2021 | Conditional Approval | THOMAS FINNILA |
| HVAC-Rough | 7/8/2021 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/8/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 7/8/2021 | Partial Inspection | MISAEL ESPARZA |
| HVAC-Rough | 7/12/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 7/12/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 7/12/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/15/2021 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 7/15/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/19/2021 | Partial Approval | THOMAS FINNILA |
| Insulation | 7/21/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Shower Pan | 7/21/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/23/2021 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/27/2021 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 8/2/2021 | Approved | ALAN MORELOS |
| Pre-Inspection | 8/2/2021 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Final | 10/12/2021 | Corrections Issued | CALEB MEISTER |
| HVAC-Final | 10/12/2021 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/2/2022 | Approved | THOMAS FINNILA |
| Final | 2/2/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 2/2/2022 | Corrections Issued | THOMAS FINNILA |
| Green Building Rough | 2/2/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 2/2/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 2/2/2022 | Corrections Issued | THOMAS FINNILA |
| Final | 4/7/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 4/7/2022 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/7/2022 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 4/7/2022 | Approved | THOMAS FINNILA |
| Final | 4/27/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 4/27/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 4/27/2022 | Approved | ARAM AVEDISIAN |
| Service/Power Release | 6/28/2022 | Approved | ARAM AVEDISIAN |