- Work Description
- CONVERT 6' x 19'10" PATIO COVER TO INTERIOR CONDITIONED SPACE, ADDITION OF 14'11" x 26'6" TO CONSIST OF NEW BEDROOM AND FULL BATHROOM, AND INTERIOR ALTERATION TO REVISE A BEDROOM LAYOUT.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- Issued on 12/2/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | LUIS RINCON |
| Corrections Issued | 10/30/2020 | LUIS RINCON |
| Applicant returned to address corrections | 12/29/2020 | LUIS RINCON |
| Applicant returned to address corrections | 10/15/2021 | LUIS RINCON |
| Building Plans Picked Up | 10/21/2021 | APPLICANT |
| Plan Check Approved | 12/1/2021 | LUIS RINCON |
| Issued | 12/2/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2021 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 8/25/2021 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/30/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael Fernandez; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/11/2022 | Approved | RAUL OLAGI |
| Deputy Drilled-In Anchors | 5/5/2022 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 5/10/2022 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 5/18/2022 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 6/13/2022 | Partial Approval | DEANDRE HOFFMAN |
| Insulation | 6/16/2022 | Approved | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 7/13/2022 | Approved | ALAN MORELOS |
| Deputy Wood Construction | 7/13/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 7/14/2022 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 7/14/2022 | Partial Approval | MATT KELLERMAN |
| Pre-Inspection | 7/14/2022 | Partial Approval | MATT KELLERMAN |
| Pre-Inspection | 8/8/2022 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 8/22/2022 | Approved | RAUL OLAGI |
| HVAC-Rough | 8/22/2022 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 8/22/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 9/13/2022 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 9/13/2022 | Partial Approval | RAUL OLAGI |
| Insulation | 9/16/2022 | Approved | RAUL OLAGI |
| Drywall Nailing | 9/21/2022 | Approved | ALAN MORELOS |
| Shower Pan | 9/21/2022 | Approved | ALAN MORELOS |
| Interior/Exterior Lathing | 10/6/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 2/16/2023 | Approved | RAUL OLAGI |
| Final | 2/16/2023 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 2/16/2023 | Approved | RAUL OLAGI |
| HVAC-Final | 2/16/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 2/16/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 2/16/2023 | Approved | RAUL OLAGI |