1041 N DEXTER ST 90042

Certificate Information: 1041 N DEXTER ST 90042

Application / Permit
20014-20000-04515
Plan Check / Job No.
B20VN13456
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (N) BEDROOM & BATHROOM TO (E) 1-STORY SFD; INTERIOR REMODEL
Permit Issued
Issued on 10/28/2021
Issuing Office
Current Status
CofO Issued on 6/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 NILOOFAR MEHRAIN
Corrections Issued 11/17/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 11/19/2020 APPLICANT
Plan Check Approved 2/24/2021 NILOOFAR MEHRAIN
Issued 10/28/2021 APPLICANT
CofO in Progress 6/13/2022 HAMIK HARTOUNIAN
Permit Finaled 6/18/2022 DEROLD HAUFF
CofO Issued 6/18/2022 DEROLD HAUFF
Permit Finaled 6/18/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/13/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 1/13/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 1/13/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 1/13/2021 RENZ SORIANO
BHO/Hillside ordinance Cleared 1/13/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 1/13/2021 RENZ SORIANO
Sewer availability Cleared 1/13/2021 RENZ SORIANO
Street Frontage Cleared 1/13/2021 RENZ SORIANO
Grading Pre-Inspection Cleared 1/15/2021 BARTON HOLMES
Hydrant and Access approval Cleared 2/12/2021 KURT CORRAL
Roof/Waste drainage to street Cleared 10/28/2021 CELINA MORENO

Contact Information

Contractor Owner-Builder       ,
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/24/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/8/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/23/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Final 12/23/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 12/28/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 1/12/2022 Approved BRIAN SULLIVAN
PLUMBING-Rough 1/12/2022 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 1/18/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 1/18/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/24/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/24/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 1/24/2022 Approved HAMIK HARTOUNIAN
Insulation 1/27/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 2/2/2022 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 6/3/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 6/3/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 6/3/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 6/3/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 6/3/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/3/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 6/3/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 6/8/2022 Approved HAMIK HARTOUNIAN
Final 6/8/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 6/8/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Final 6/8/2022 Approved HAMIK HARTOUNIAN
Final 6/13/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 6/13/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 6/13/2022 SGSOV Approved HAMIK HARTOUNIAN