6634 N SATSUMA AVE 91606
Certificate Information: 6634 N SATSUMA AVE 91606
- Application / Permit
- 20014-20000-04502
- Plan Check / Job No.
- B20VN13441
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AND 174 SF 1ST FLOOR AND 551 SF 2ND FLOOR ADDITION PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 2/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/19/2020 | COLIN LOREDO |
| Corrections Issued | 11/25/2020 | COLIN LOREDO |
| Quality Review Completed | 11/30/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
| Applicant returned to address corrections | 2/9/2021 | COLIN LOREDO |
| Applicant returned to address corrections | 6/18/2021 | COLIN LOREDO |
| Plan Check Approved | 1/12/2022 | COLIN LOREDO |
| Issued | 1/12/2022 | APPLICANT |
| CofO in Progress | 1/17/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
| CofO Issued | 2/6/2025 | RUBEN SALAS |
| Permit Finaled | 2/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 4/7/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 6/19/2021 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 12/30/2021 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 1/4/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Armando; Lic. No.: C83911 | 121 N VAIL AVE MONTEBELLO, CA 90640 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/8/2022 | Corrections Issued | JACK KARGODORIAN |
| Underground Mechanical | 2/8/2022 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/10/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 2/15/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 2/18/2022 | Approved | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 3/7/2022 | Partial Approval | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Conditional Approval | THOMAS FINNILA |
| Deputy Wood Construction | 4/1/2022 | Conditional Approval | CALEB MEISTER |
| ELECTRICAL-Rough | 4/12/2022 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Partial Approval | CALEB MEISTER |
| PLUMBING-Rough | 4/12/2022 | Approved | CALEB MEISTER |
| Wood Frame | 4/12/2022 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/19/2022 | Corrections Issued | CALEB MEISTER |
| Insulation | 4/19/2022 | Not Ready for Inspection | CALEB MEISTER |
| Interior/Exterior Lathing | 4/19/2022 | Partial Approval | CALEB MEISTER |
| Drywall Nailing | 4/22/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 4/22/2022 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Not Ready | JOHN HAYES |
| BUILDING-Rough-Frame | 9/30/2022 | No Access for Inspection | JOHN HAYES |
| Final | 9/30/2022 | No Access for Inspection | JOHN HAYES |
| Green Building Final | 9/30/2022 | No Access for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/30/2022 | No Access for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 10/13/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 10/13/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 10/13/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 10/13/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 10/13/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 11/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/17/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 11/17/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/17/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/17/2022 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/29/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/29/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/29/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/29/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/29/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 3/7/2023 | SGSOV Not Ready | JOHN HAYES |
| BUILDING-Rough-Frame | 3/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 3/13/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 3/13/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 3/13/2023 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 3/13/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 3/24/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Final | 3/24/2023 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 5/12/2023 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/12/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 1/23/2024 | Not Ready for Inspection | ROBERT GOLD |
| Final | 1/23/2024 | Partial Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 5/2/2024 | Not Ready for Inspection | JOHN HAYES |
| Final | 5/2/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 5/2/2024 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 5/2/2024 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/12/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 7/12/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 8/14/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 8/14/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 1/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 1/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 1/16/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/16/2025 | Approved | ROBERTO PALACIOS-LOPEZ |