16112 W MEADOW VIEW DR 91436

Certificate Information: 16112 W MEADOW VIEW DR 91436

Application / Permit
20014-20000-04496
Plan Check / Job No.
B20VN13429
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDIITON OF 2ND STORY TO (E) GARAGE TO CREATE A NEW BEDROOM
Permit Issued
Issued on 3/14/2022
Issuing Office
Current Status
CofO Issued on 2/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2020 APPLICANT
Assigned to Plan Check Engineer 11/12/2020 MOHAMMAD ESMAILI
Corrections Issued 11/17/2020 MOHAMMAD ESMAILI
Quality Review Completed 12/11/2020 OMID HEDAYAT
Building Plans Picked Up 12/16/2020 APPLICANT
Applicant returned to address corrections 1/31/2022 MOHAMMAD ESMAILI
Plan Check Approved 3/14/2022 MOHAMMAD ESMAILI
Issued 3/14/2022 APPLICANT
CofO in Progress 1/18/2024 VINCENT HANLEY
Permit Finaled 2/14/2024 JOHN JANSON
CofO Issued 2/14/2024 JOHN JANSON
Permit Finaled 2/14/2024 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
BHO/Hillside ordinance Cleared 2/1/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/2/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 2/2/2022 DAGOVERTO GUERRERO
Miscellaneous Cleared 2/3/2022 ANNA VIDAL
Low Impact Development Cleared 2/28/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 3/1/2022 DAGOVERTO GUERRERO
GPI Written Notices Cleared 3/14/2022 MOHAMMAD ESMAILI
Grading Pre-Inspection Cleared 3/14/2022 MOHAMMAD ESMAILI

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 6/22/2022 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 7/5/2022 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 7/5/2022 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 7/6/2022 Conditional Approval MORRIS JACKSON
Deputy Drilled-In Anchors 7/20/2022 Conditional Approval JOHN JANSON
Deputy Other (see comments) 7/20/2022 Conditional Approval JOHN JANSON
Excavation/Setback/Form/Re-Bar 7/25/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 7/25/2022 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 7/26/2022 Approved VINCENT HANLEY
Deputy Reinf. Concrete 7/26/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Partial Approval VINCENT HANLEY
Wood Frame 8/5/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/6/2022 Approved VINCENT HANLEY
Green Building Rough 10/6/2022 Approved VINCENT HANLEY
Rough-Elec/Plmb/HVAC 10/6/2022 Approved VINCENT HANLEY
Insulation 10/19/2022 Conditional Approval JESUS PINEDA
Interior/Exterior Lathing 10/19/2022 Partial Approval JESUS PINEDA
Shower Pan 10/19/2022 Approved JESUS PINEDA
Drywall Nailing 10/27/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 10/27/2022 Approved JESUS PINEDA
Final 9/21/2023 Corrections Issued VINCENT HANLEY
ELECTRICAL-Final 1/17/2024 Approved VINCENT HANLEY
Final 1/17/2024 OK to Issue CofO VINCENT HANLEY
Footing/Foundation/Slab 1/17/2024 Approved VINCENT HANLEY
Green Building Final 1/17/2024 Approved VINCENT HANLEY
HVAC-Final 1/17/2024 Approved VINCENT HANLEY
PLUMBING-Final 1/17/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/17/2024 SGSOV Approved VINCENT HANLEY
Smoke Detectors 1/17/2024 Approved VINCENT HANLEY