7505 N ZELZAH AVE 91335

Certificate Information: 7505 N ZELZAH AVE 91335

Application / Permit
20014-20000-04495
Plan Check / Job No.
B20VN13426
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION (12'-6"x20'-0") TO AND CONVERT THE (E) 20'-0"x20'-0") GARAGE INTO A (N) ACCESSORY DWELLING UNIT. PER LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 2/12/2021
Issuing Office
Current Status
CofO Issued on 5/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 MOHAMMAD ESMAILI
Corrections Issued 11/1/2020 MOHAMMAD ESMAILI
Building Plans Picked Up 11/4/2020 APPLICANT
Plan Check Approved 2/10/2021 MOHAMMAD ESMAILI
Issued 2/12/2021 APPLICANT
CofO in Progress 5/20/2021 VINCENT HANLEY
Permit Finaled 5/20/2021 JOHN JANSON
CofO Issued 5/20/2021 JOHN JANSON
Permit Finaled 5/20/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/7/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/7/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/8/2021 ADRIAN CASTRO
Sewer availability Cleared 1/8/2021 ADRIAN CASTRO

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/26/2021 Partial Approval VINCENT HANLEY
Sewer 2/26/2021 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 3/1/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 3/3/2021 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 3/9/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/15/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 3/25/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/26/2021 Approved VINCENT HANLEY
ELECTRICAL-Rough 3/26/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Approved VINCENT HANLEY
Green Building Rough 3/26/2021 Approved VINCENT HANLEY
PLUMBING-Rough 3/26/2021 Approved VINCENT HANLEY
Insulation 4/7/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/7/2021 Approved VINCENT HANLEY
Shower Pan 4/7/2021 Approved VINCENT HANLEY
Drywall Nailing 4/16/2021 Approved VINCENT HANLEY
HVAC-Final 5/10/2021 Corrections Issued STEVEN BACK
Final 5/20/2021 OK to Issue CofO VINCENT HANLEY
Green Building Final 5/20/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/20/2021 SGSOV Approved VINCENT HANLEY
Smoke Detectors 5/20/2021 Approved VINCENT HANLEY