15477 W DICKENS ST 91403

Certificate Information: 15477 W DICKENS ST 91403

Application / Permit
20014-20000-04483
Plan Check / Job No.
B20VN13393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
64'4"X45'0" IRREGULAR SHAPED ADDITION WITH 6'10"X5'10" PORCH & MAJOR REMODEL TO (E) SFD. NFPA 13 D FIRE SPRINKLERS REQ'D - 1 OF 2
Permit Issued
Issued on 4/5/2021
Issuing Office
Current Status
CofO Issued on 11/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 MARVEL DELACRUZ
Corrections Issued 10/17/2020 MARVEL DELACRUZ
Quality Review Completed 10/23/2020 STEVEN KIM
Building Plans Picked Up 10/23/2020 APPLICANT
Applicant returned to address corrections 2/1/2021 MARVEL DELACRUZ
Plan Check Approved 3/9/2021 MARVEL DELACRUZ
Issued 4/5/2021 APPLICANT
CofO in Progress 10/3/2022 VINCENT HANLEY
Permit Finaled 11/16/2022 JOHN JANSON
CofO Issued 11/16/2022 JOHN JANSON
Permit Finaled 11/16/2022 JOHN JANSON

Permit Application Clearance Information

Permit Cleared 11/4/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/9/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/9/2020 JOHN TRIANTAFYLLOS
Trees in Parkway Cleared 12/3/2020 JOHN KIM
Low Impact Development Cleared 12/10/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 12/14/2020 JOHN TRIANTAFYLLOS
GPI Written Notices Cleared 2/1/2021 MARVEL DELACRUZ
Green Code Cleared 2/1/2021 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 2/4/2021 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/22/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 5/4/2021 Partial Approval VINCENT HANLEY
PLUMBING-Rough 5/4/2021 Partial Approval VINCENT HANLEY
HVAC-Rough 5/7/2021 Not Ready for Inspection DAVID STEPANYAN
Insulation 5/7/2021 Partial Approval DAVID STEPANYAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2021 Partial Approval RONALD COWAN
Drywall Nailing 6/18/2021 Not Ready for Inspection RONALD COWAN
Green Building Rough 6/18/2021 Not Ready for Inspection RONALD COWAN
ELECTRICAL-Rough 7/14/2021 Approved RONALD COWAN
HVAC-Rough 7/14/2021 Approved RONALD COWAN
Interior/Exterior Lathing 7/14/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 7/14/2021 Approved RONALD COWAN
Green Building Rough 7/20/2021 Approved RONALD COWAN
Interior/Exterior Lathing 7/20/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 7/30/2021 Approved RONALD COWAN
MERV13>=Rough 7/30/2021 Approved RONALD COWAN
Verify Sprinkler Sign Off 7/30/2021 Approved RONALD COWAN
Insulation 8/4/2021 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 8/13/2021 Approved RONALD COWAN
Insulation 8/13/2021 Approved RONALD COWAN
Final 3/24/2022 Corrections Issued PETER FOLLING
Footing/Foundation/Slab 3/24/2022 Approved PETER FOLLING
Green Building Final 3/24/2022 Not Ready for Inspection PETER FOLLING
MERV13>=Final 3/24/2022 Not Ready for Inspection PETER FOLLING
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Not Ready PETER FOLLING
Smoke Detectors 3/24/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Final 4/1/2022 Not Ready for Inspection PETER FOLLING
Final 4/1/2022 Corrections Issued PETER FOLLING
Green Building Final 4/1/2022 Not Ready for Inspection PETER FOLLING
HVAC-Final 4/1/2022 Corrections Issued PETER FOLLING
MERV13>=Final 4/1/2022 Not Ready for Inspection PETER FOLLING
PLUMBING-Final 4/1/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 4/1/2022 SGSOV Not Ready PETER FOLLING
Smoke Detectors 4/1/2022 Approved PETER FOLLING
ELECTRICAL-Final 9/19/2022 Approved VINCENT HANLEY
Green Building Final 9/19/2022 Approved VINCENT HANLEY
HVAC-Final 9/19/2022 Not Ready for Inspection VINCENT HANLEY
MERV13>=Final 9/19/2022 Approved VINCENT HANLEY
Service/Power Release 9/19/2022 Approved VINCENT HANLEY
Final 9/30/2022 OK to Issue CofO VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 9/30/2022 SGSOV Approved VINCENT HANLEY