17501 W EMELITA ST 91316

Certificate Information: 17501 W EMELITA ST 91316

Application / Permit
20014-20000-04477
Plan Check / Job No.
B20VN13383
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 46'1" X 33'11" IRREGULAR SHAPED ADDITION TO (E) SFD TO RELOCATE KITCHEN , FAMILY ROOM , , CREATE NEW BEDROOMS , BATHROOM AND W.I.C., NEW LAUNDRY , ENLARGE DINING ROOM & INTERIOR REMODEL TO (E) 1-STORY SFD TO REMODEL (2) BEDROOMS , (1) BATHROOM , LIVING , DINING ROOM AND KITCHEN , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/3/2021
Issuing Office
Current Status
Issued on 3/3/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/14/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 RARES BODEA
Corrections Issued 11/7/2020 RARES BODEA
Quality Review Completed 11/13/2020 STEVEN KIM
Building Plans Picked Up 11/16/2020 APPLICANT
Plan Check Approved 3/2/2021 RARES BODEA
Issued 3/3/2021 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/17/2020 THOMAS LANG
Sewer availability Cleared 11/17/2020 THOMAS LANG
ZI Cleared 12/1/2020 PABLO ESTRADA
Low Impact Development Cleared 1/26/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/26/2021 THOMAS LANG
Hydrant and Access approval Cleared 2/10/2021 ROBERT DUFF

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2021 Approved STEVEN BACK
Footing/Foundation/Slab 3/9/2021 Approved STEVEN BACK
Deputy Reinf. Concrete 3/11/2021 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 3/26/2021 Partial Approval STEVEN BACK
PLUMBING-Rough 3/26/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval RONALD COWAN
Insulation 4/1/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 4/21/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 4/21/2021 Partial Approval STEVEN BACK
Green Building Rough 4/21/2021 Not Ready for Inspection STEVEN BACK
HVAC-Rough 5/7/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 5/12/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 5/12/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Corrections Issued STEVEN BACK
Green Building Rough 5/12/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 5/12/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 5/12/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 5/21/2021 Conditional Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/21/2021 Approved STEVEN BACK
Green Building Rough 5/21/2021 Not Ready for Inspection STEVEN BACK
Shower Pan 5/21/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 5/21/2021 Partial Approval STEVEN BACK
Green Building Rough 5/26/2021 Approved STEVEN BACK
Interior/Exterior Lathing 5/26/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 6/30/2021 Approved STEVEN BACK
Drywall Nailing 6/30/2021 Approved STEVEN BACK
Insulation 6/30/2021 Approved STEVEN BACK
Verify Sprinkler Sign Off 6/30/2021 Approved STEVEN BACK
ELECTRICAL-Final 9/1/2021 Not Ready for Inspection STEVEN BACK
Final 9/1/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Final 9/14/2021 Approved STEVEN BACK
Service/Power Release 9/14/2021 Approved STEVEN BACK
Final 11/2/2021 Corrections Issued SEAN HAUPT
Green Building Final 11/2/2021 Not Ready for Inspection SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 11/2/2021 SGSOV Approved SEAN HAUPT
Smoke Detectors 11/2/2021 Not Ready for Inspection SEAN HAUPT
Final 11/9/2021 Conditional Approval SEAN HAUPT
Green Building Final 11/9/2021 Approved SEAN HAUPT
Smoke Detectors 11/9/2021 Approved SEAN HAUPT