3634 1/2 W 59TH ST 90043
Certificate Information: 3634 1/2 W 59TH ST 90043
- Application / Permit
- 20014-20000-04454
- Plan Check / Job No.
- B20VN13311
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 27'-6" X 20'-7" TO AND CONVERT EXISTING 18' X 18' DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 2/20/2021
- Issuing Office
- Current Status
- CofO Issued on 9/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2020 | SELLA BENYAMIN |
| Corrections Issued | 11/10/2020 | SELLA BENYAMIN |
| Building Plans Picked Up | 11/17/2020 | APPLICANT |
| Issued | 2/20/2021 | APPLICANT |
| CofO in Progress | 9/8/2023 | ENRIQUE MIRELES |
| CofO in Progress | 9/8/2023 | ENRIQUE MIRELES |
| CofO Issued | 9/13/2023 | DEROLD HAUFF |
| Permit Finaled | 9/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/24/2020 | CELINA MORENO |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/30/2020 | CELINA MORENO |
| Sewer availability | Cleared | 11/30/2020 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 12/18/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Pre-Inspection | 3/19/2021 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 4/9/2021 | Conditional Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 4/9/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2021 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 9/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 10/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Final | 10/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 10/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 10/14/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/14/2021 | Partial Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/10/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 2/10/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/10/2022 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/15/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/15/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 2/15/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/15/2022 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 2/15/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/15/2022 | Conditional Approval | FREDDIE RIVERA |
| Drywall Nailing | 2/28/2022 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 3/3/2022 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 3/9/2022 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 3/15/2022 | Approved | HORACE FULTZ |
| Sewer | 9/28/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/17/2022 | Corrections Issued | ENRIQUE MIRELES |
| Gas Test | 2/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/14/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Gas Test | 2/17/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 2/17/2023 | Approved | ENRIQUE MIRELES |
| Gas Test | 2/23/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 4/17/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 4/24/2023 | Approved | ENRIQUE MIRELES |
| Final | 7/6/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Footing/Foundation/Slab | 7/6/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Green Building Final | 7/6/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Smoke Detectors | 7/6/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Final | 7/7/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/7/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 7/7/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 7/7/2023 | Approved | ENRIQUE MIRELES |
| Final | 8/31/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 9/6/2023 | OK to Issue CofO | ENRIQUE MIRELES |