954-956 S WINDSOR BLVD 90019
Certificate Information: 954-956 S WINDSOR BLVD 90019
- Application / Permit
- 20014-20000-04453
- Plan Check / Job No.
- B20VN13310
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 23'-6" X 16'-4" ADDITION TO AND CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e) FOR (E) SFD. WORK PER WFPP.
- Permit Issued
- Issued on 5/24/2021
- Issuing Office
- Current Status
- CofO Issued on 7/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2020 | ROSENDO MEDINA |
| Corrections Issued | 10/21/2020 | ROSENDO MEDINA |
| Applicant returned to address corrections | 5/14/2021 | ROSENDO MEDINA |
| Plan Check Approved | 5/21/2021 | ROSENDO MEDINA |
| Issued | 5/24/2021 | APPLICANT |
| Building Plans Picked Up | 5/24/2021 | APPLICANT |
| CofO in Progress | 6/30/2023 | JEFFREY MEAD |
| Permit Finaled | 7/2/2023 | DEROLD HAUFF |
| CofO Issued | 7/2/2023 | DEROLD HAUFF |
| Permit Finaled | 7/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2020 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 10/28/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 10/28/2020 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 10/28/2020 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 10/28/2020 | LEE GUILBEAUX |
| HPOZ | Cleared | 4/22/2021 | AMANDA KAINER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2022 | Conditional Approval | JOSEPH MCGARRY |
| METHANE-Barrier | 1/11/2022 | Approved | JOSEPH MCGARRY |
| METHANE-Subgrade | 1/11/2022 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/11/2022 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 1/11/2022 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Rough | 4/1/2022 | Partial Approval | SHAVONNE ESPINOZA |
| Green Building Rough | 4/1/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| HVAC-Rough | 4/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| METHANE-Rough | 4/1/2022 | Approved | SHAVONNE ESPINOZA |
| PLUMBING-Rough | 4/1/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| BUILDING-Rough-Frame | 4/7/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 4/7/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Rough-Elec/Plmb/HVAC | 4/7/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 4/11/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 4/14/2022 | Approved | STUART CHAPMAN |
| Insulation | 4/14/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 4/22/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 4/27/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 5/18/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| ELECTRICAL-Final | 9/20/2022 | Corrections Issued | JEFFREY MEAD |
| Final | 9/20/2022 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 9/20/2022 | Approved | JEFFREY MEAD |
| Green Building Final | 9/20/2022 | Approved | JEFFREY MEAD |
| HVAC-Final | 9/20/2022 | Partial Approval | JEFFREY MEAD |
| PLUMBING-Final | 9/20/2022 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 9/20/2022 | SGSOV Not Ready | JEFFREY MEAD |
| Smoke Detectors | 9/20/2022 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 10/19/2022 | Approved | JEFFREY MEAD |
| Final | 10/19/2022 | Corrections Issued | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/19/2022 | SGSOV Approved | JEFFREY MEAD |
| Final | 6/29/2023 | Partial Approval | JEFFREY MEAD |
| HVAC-Final | 6/29/2023 | Approved | JEFFREY MEAD |
| Final | 6/30/2023 | OK to Issue CofO | JEFFREY MEAD |