16322 W PLUMMER ST 91343
Certificate Information: 16322 W PLUMMER ST 91343
- Application / Permit
- 20014-20000-04445
- Plan Check / Job No.
- B20VN13290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD 18' 4" X 14' TO DETACHED GARAGE AND CONVERT TO ADU. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 12/22/2020
- Issuing Office
- Current Status
- CofO Issued on 11/12/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 10/14/2020 | GURUNATH NESARAJAH |
| Plan Check Approved | 12/22/2020 | GURUNATH NESARAJAH |
| Issued | 12/22/2020 | APPLICANT |
| CofO in Progress | 11/4/2022 | RAUL OLAGI |
| Permit Finaled | 11/12/2022 | MICHAEL SMITH |
| CofO Issued | 11/12/2022 | MICHAEL SMITH |
| Permit Finaled | 11/12/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/23/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 11/23/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 11/23/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/23/2020 | GUILLERMO PETRA |
| Grading Pre-Inspection | Cleared | 12/1/2020 | BARTON HOLMES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 2/25/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Underground Mechanical | 2/25/2021 | Approved | ARTHUR SARGSYAN |
| Deputy Drilled-In Anchors | 2/26/2021 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/2/2021 | Approved | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/2/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 4/6/2021 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2021 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 4/6/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 4/20/2021 | Corrections Issued | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Gas Test | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/1/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/8/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/8/2021 | Approved | ARTHUR SARGSYAN |
| Insulation | 6/17/2021 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/17/2021 | Not Ready for Inspection | JAVIER RAMOS JR |
| Insulation | 6/22/2021 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/22/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Drywall Nailing | 6/29/2021 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/29/2021 | Approved | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Not Ready | RAUL OLAGI |
| Gas Test | 2/4/2022 | Corrections Issued | RAUL OLAGI |
| Service/Power Release | 2/4/2022 | Corrections Issued | RAUL OLAGI |
| Gas Test | 3/18/2022 | Not Ready for Inspection | RAUL OLAGI |
| Service/Power Release | 3/18/2022 | Corrections Issued | RAUL OLAGI |
| Gas Test | 3/30/2022 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/4/2022 | Approved | RAUL OLAGI |
| Final | 11/4/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 11/4/2022 | Approved | RAUL OLAGI |
| Green Building Rough | 11/4/2022 | Approved | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 11/4/2022 | Approved | RAUL OLAGI |