1900 W 91ST ST 90047

Certificate Information: 1900 W 91ST ST 90047

Application / Permit
20014-20000-04437
Plan Check / Job No.
B20VN13277
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 19'11"X16'1" BEDRM & CLOSET ADDITION AT REAR. CONVERT EX BEDRM INTO BATHRM. ALL WORK PER ENGR DESIGN.
Permit Issued
Issued on 12/11/2020
Issuing Office
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 HAYATO TSUCHIYA
Corrections Issued 10/16/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 11/18/2020 HAYATO TSUCHIYA
Plan Check Approved 11/24/2020 HAYATO TSUCHIYA
Issued 12/11/2020 APPLICANT
CofO in Progress 8/14/2021 FREDDIE RIVERA
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/28/2020 JUAN ASHTON
Sewer availability Cleared 10/28/2020 JUAN ASHTON
Eng Process Fee Ord 176,300 Cleared 10/29/2020 JUAN ASHTON

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/7/2021 Approved FREDDIE RIVERA
METHANE-Barrier 1/7/2021 Approved FREDDIE RIVERA
METHANE-Subgrade 1/7/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 1/15/2021 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/27/2021 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 2/8/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 2/8/2021 Approved FREDDIE RIVERA
Green Building Rough 2/8/2021 Approved FREDDIE RIVERA
METHANE-Rough 2/8/2021 Approved FREDDIE RIVERA
Insulation 2/19/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 2/19/2021 Approved FREDDIE RIVERA
Drywall Nailing 3/1/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 3/18/2021 Approved FREDDIE RIVERA
Final 8/13/2021 OK to Issue CofO FREDDIE RIVERA
Green Building Final 8/13/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/13/2021 SGSOV Approved FREDDIE RIVERA
Service/Power Release 8/13/2021 Approved FREDDIE RIVERA
Smoke Detectors 8/13/2021 Approved FREDDIE RIVERA