15144 W HARTSOOK ST 91403
Certificate Information: 15144 W HARTSOOK ST 91403
- Application / Permit
- 20014-20000-04407
- Plan Check / Job No.
- B20VN13231
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 5'-1" X 16'-4" & 8'-5" X 4' TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 4/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2020 | RAPHAEL ROSAS |
| Corrections Issued | 10/22/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 11/17/2020 | RAPHAEL ROSAS |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 3/17/2021 | CHRISTOPHE COCHRAN |
| CofO in Progress | 3/18/2021 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
| CofO Issued | 4/17/2021 | MICHAEL SMITH |
| Permit Finaled | 4/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/5/2020 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 11/9/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | JOHN TRIANTAFYLLOS |
| ZI | Cleared | 11/23/2020 | RICHARD REASER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Boules,, George Helmy; Lic. No.: C64144 | 20016 LULL ST WINNETKA, CA 91306 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/24/2020 | Corrections Issued | JOHN HAYES |
| Insulation | 1/27/2021 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 1/27/2021 | Approved | ARTHUR SARGSYAN |
| Rough-Elec/Plmb/HVAC | 1/27/2021 | Approved | ARTHUR SARGSYAN |
| Wood Frame | 1/27/2021 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 2/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| Final | 2/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| Footing/Foundation/Slab | 2/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Final | 2/22/2021 | Corrections Issued | CHARLES POWELL |
| Green Building Rough | 2/22/2021 | Not Ready for Inspection | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 2/22/2021 | SGSOV Not Ready | CHARLES POWELL |
| Smoke Detectors | 2/22/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 3/8/2021 | Partial Approval | CHARLES POWELL |
| Final | 3/8/2021 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 3/8/2021 | Approved | CHARLES POWELL |
| Green Building Final | 3/8/2021 | Not Ready for Inspection | CHARLES POWELL |
| Green Building Rough | 3/8/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/8/2021 | SGSOV Not Ready | CHARLES POWELL |
| BUILDING-Rough-Frame | 3/16/2021 | Approved | CHARLES POWELL |
| Final | 3/16/2021 | OK to Issue CofO | CHARLES POWELL |
| Green Building Final | 3/16/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/16/2021 | SGSOV Approved | CHARLES POWELL |