15144 W HARTSOOK ST 91403

Certificate Information: 15144 W HARTSOOK ST 91403

Application / Permit
20014-20000-04407
Plan Check / Job No.
B20VN13231
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 5'-1" X 16'-4" & 8'-5" X 4' TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofO Issued on 4/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 RAPHAEL ROSAS
Corrections Issued 10/22/2020 RAPHAEL ROSAS
Applicant returned to address corrections 11/17/2020 RAPHAEL ROSAS
Issued 12/9/2020 APPLICANT
CofO in Progress 3/17/2021 CHRISTOPHE COCHRAN
CofO in Progress 3/18/2021 CHRISTOPHE COCHRAN
Permit Finaled 4/17/2021 MICHAEL SMITH
CofO Issued 4/17/2021 MICHAEL SMITH
Permit Finaled 4/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/9/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/18/2020 JOHN TRIANTAFYLLOS
ZI Cleared 11/23/2020 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,
Engineer Boules,, George Helmy; Lic. No.: C64144 20016 LULL ST      WINNETKA, CA 91306

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/24/2020 Corrections Issued JOHN HAYES
Insulation 1/27/2021 Approved ARTHUR SARGSYAN
PLUMBING-Rough 1/27/2021 Approved ARTHUR SARGSYAN
Rough-Elec/Plmb/HVAC 1/27/2021 Approved ARTHUR SARGSYAN
Wood Frame 1/27/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 2/22/2021 Not Ready for Inspection CHARLES POWELL
Final 2/22/2021 Not Ready for Inspection CHARLES POWELL
Footing/Foundation/Slab 2/22/2021 Not Ready for Inspection CHARLES POWELL
Green Building Final 2/22/2021 Corrections Issued CHARLES POWELL
Green Building Rough 2/22/2021 Not Ready for Inspection CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Not Ready CHARLES POWELL
Smoke Detectors 2/22/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 3/8/2021 Partial Approval CHARLES POWELL
Final 3/8/2021 Corrections Issued CHARLES POWELL
Footing/Foundation/Slab 3/8/2021 Approved CHARLES POWELL
Green Building Final 3/8/2021 Not Ready for Inspection CHARLES POWELL
Green Building Rough 3/8/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 3/8/2021 SGSOV Not Ready CHARLES POWELL
BUILDING-Rough-Frame 3/16/2021 Approved CHARLES POWELL
Final 3/16/2021 OK to Issue CofO CHARLES POWELL
Green Building Final 3/16/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 3/16/2021 SGSOV Approved CHARLES POWELL