4048 W EDENHURST AVE 90039
Certificate Information: 4048 W EDENHURST AVE 90039
- Application / Permit
- 20014-20000-04393
- Plan Check / Job No.
- B20VN13195
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF IRREGULAR 17'9" x 28' AND A 7.5' x 15' CARPORT. INTERIOR ALTERATION TO INCLUDE REMODELING THE KITCHEN AND REVISING THE FLOOR PLAN AND CREATING A NEW FULL BATHROOM.
- Permit Issued
- Issued on 4/16/2021
- Issuing Office
- Current Status
- CofO Issued on 4/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2020 | LUIS RINCON |
| Corrections Issued | 10/16/2020 | LUIS RINCON |
| Applicant returned to address corrections | 12/15/2020 | LUIS RINCON |
| Applicant returned to address corrections | 1/27/2021 | LUIS RINCON |
| Applicant returned to address corrections | 3/1/2021 | LUIS RINCON |
| Plan Check Approved | 4/16/2021 | LUIS RINCON |
| Issued | 4/16/2021 | APPLICANT |
| Building Plans Picked Up | 4/20/2021 | APPLICANT |
| CofO in Progress | 2/11/2022 | HAMIK HARTOUNIAN |
| CofO in Progress | 2/14/2022 | HAMIK HARTOUNIAN |
| CofO in Progress | 3/23/2023 | HAMIK HARTOUNIAN |
| Permit Finaled | 4/2/2023 | DEROLD HAUFF |
| CofO Issued | 4/2/2023 | DEROLD HAUFF |
| Permit Finaled | 4/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 11/18/2020 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2020 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 12/2/2020 | THOMAS LANG |
Contact Information
| Contractor | Eden Builders; Lic. No.: 891510-B | 19528 VENTURA BLVD UNIT 242 TARZANA, CA 91356 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/12/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/20/2021 | Partial Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/4/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 6/4/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 6/4/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Wood Construction | 7/20/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/4/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 8/4/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Partial Approval | HAMIK HARTOUNIAN |
| Green Building Rough | 8/4/2021 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 8/4/2021 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 8/4/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 8/13/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 8/24/2021 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 8/24/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Drywall Nailing | 9/3/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 9/3/2021 | Approved | DAVID FEILER |
| Final | 2/8/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Green Building Final | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 2/8/2022 | Approved | HAMIK HARTOUNIAN |
| Final | 6/9/2022 | No Access for Inspection | HAMIK HARTOUNIAN |
| Final | 7/14/2022 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 3/23/2023 | OK to Issue CofO | HAMIK HARTOUNIAN |