9730 N LEV AVE 91331

Certificate Information: 9730 N LEV AVE 91331

Application / Permit
20014-20000-04392
Plan Check / Job No.
B20VN13194
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (N) BEDROOM, BATHROOM & FAMILY ROOM (25' X 20') AND PATIO COVER (14'-6" X 25') TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL (ALL WORK PER WFPP)
Permit Issued
Issued on 12/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 NILOOFAR MEHRAIN
Corrections Issued 10/20/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 10/22/2020 APPLICANT
Issued 12/10/2020 APPLICANT
CofO in Progress 7/22/2021 MICHEL ABAJAN
CofO Issued 9/4/2021 MICHAEL SMITH
Permit Finaled 9/4/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/5/2020 ADRIAN CASTRO
Sewer availability Cleared 11/5/2020 ADRIAN CASTRO
Low Impact Development Cleared 11/19/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/2/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/4/2021 Approved MICHEL ABAJAN
Footing/Foundation/Slab 2/4/2021 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 2/4/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 2/4/2021 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 2/10/2021 Approved MICHEL ABAJAN
METHANE-Subgrade 2/10/2021 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 2/24/2021 Partial Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/24/2021 Partial Approval MICHEL ABAJAN
Green Building Rough 2/24/2021 Partial Inspection MICHEL ABAJAN
MERV13>=Rough 2/24/2021 Partial Inspection MICHEL ABAJAN
METHANE-Rough 2/24/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/4/2021 Approved MICHEL ABAJAN
Green Building Rough 3/4/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/4/2021 Approved MICHEL ABAJAN
MERV13>=Rough 3/4/2021 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 3/4/2021 Approved MICHEL ABAJAN
Insulation 3/8/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/8/2021 Approved MICHEL ABAJAN
Shower Pan 3/8/2021 Approved MICHEL ABAJAN
Drywall Nailing 3/10/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 4/30/2021 Approved MICHEL ABAJAN
Final 4/30/2021 Corrections Issued MICHEL ABAJAN
HVAC-Final 4/30/2021 Approved MICHEL ABAJAN
MERV13>=Final 4/30/2021 Approved MICHEL ABAJAN
PLUMBING-Final 4/30/2021 Approved MICHEL ABAJAN
Smoke Detectors 4/30/2021 Approved MICHEL ABAJAN
Final 7/22/2021 OK to Issue CofO MICHEL ABAJAN
Green Building Final 7/22/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/22/2021 SGSOV Approved MICHEL ABAJAN