1746 N AVENUE 46 90041

Certificate Information: 1746 N AVENUE 46 90041

Application / Permit
20014-20000-04380
Plan Check / Job No.
B20VN13149
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE GARAGE (330 SQ FT); ADD NEW 10' X 33' CARPORT; 17' X 33' ADDITION TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL; EQUIPPED WITH NFPA-13D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 4/13/2021
Issuing Office
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 SELLA BENYAMIN
Corrections Issued 11/2/2020 SELLA BENYAMIN
Quality Review Completed 11/6/2020 STEVEN KIM
Building Plans Picked Up 11/6/2020 APPLICANT
Plan Check Approved 4/13/2021 SELLA BENYAMIN
Issued 4/13/2021 APPLICANT
CofO in Progress 2/10/2023 CRAIG VAUGHAN
Permit Finaled 3/22/2023 DEROLD HAUFF
CofO Issued 3/22/2023 DEROLD HAUFF
Permit Finaled 3/22/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/20/2020 CECILIO NAVARRO
Sewer availability Cleared 11/20/2020 CECILIO NAVARRO
Low Impact Development Cleared 3/26/2021 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/31/2021 CECILIO NAVARRO
GPI Written Notices Cleared 4/13/2021 SELLA BENYAMIN
Grading Pre-Inspection Cleared 4/13/2021 SELLA BENYAMIN

Contact Information

Contractor Regal Construction & Remodeling Inc; Lic. No.: 909023-B 19537.5 VENTURA BLVD      TARZANA, CA 91356
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/17/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/17/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 5/17/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/18/2021 Corrections Issued CRAIG VAUGHAN
Underground Mechanical 5/18/2021 Partial Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 5/21/2021 Approved SHAWN ESHBACH
BUILDING-Rough-Frame 6/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Rough 6/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 6/15/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/26/2021 Partial Approval CRAIG VAUGHAN
HVAC-Rough 7/26/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/26/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/1/2021 Approved CRAIG VAUGHAN
Green Building Rough 9/1/2021 Approved CRAIG VAUGHAN
Wood Frame 9/1/2021 Approved CRAIG VAUGHAN
Insulation 9/7/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/7/2021 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 9/13/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Shower Pan 9/13/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 9/15/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 9/15/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 10/3/2022 Corrections Issued CRAIG VAUGHAN
Final 10/3/2022 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 10/3/2022 Approved CRAIG VAUGHAN
Green Building Final 10/3/2022 Approved CRAIG VAUGHAN
HVAC-Final 10/3/2022 Corrections Issued CRAIG VAUGHAN
PLUMBING-Final 10/3/2022 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/3/2022 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/3/2022 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/9/2023 Approved CRAIG VAUGHAN
Final 2/9/2023 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 2/9/2023 Approved CRAIG VAUGHAN
HVAC-Final 2/9/2023 Approved CRAIG VAUGHAN