6128-6130 N CASE AVE 91606

Certificate Information: 6128-6130 N CASE AVE 91606

Application / Permit
20014-20000-04372
Plan Check / Job No.
B20VN13133
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATT GARAGE & PORTION OF EX DWELLING (KITCHEN) INTO ACCESSORY DWELLING UNIT PER ORD #186,481. PROPOSED NEW 24'X20' BEDRM/BATHRM/CLOSET/KITCHEN ADDITION TO MAIN DWELLING AT REAR & REMODEL EX BATHRM. ALL WORK PER WFPP.
Permit Issued
Issued on 12/30/2020
Issuing Office
Current Status
CofO Issued on 7/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2020 APPLICANT
Assigned to Plan Check Engineer 10/15/2020 HAYATO TSUCHIYA
Corrections Issued 10/18/2020 HAYATO TSUCHIYA
Plan Check Approved 12/30/2020 HAYATO TSUCHIYA
Issued 12/30/2020 APPLICANT
CofO in Progress 6/14/2021 ARAM AVEDISIAN
CofO Issued 7/10/2021 MICHAEL SMITH
Permit Finaled 7/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/4/2020 JOHN TRIANTAFYLLOS
Permit Cleared 11/4/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 11/5/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 12/8/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/22/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/4/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/7/2021 Partial Approval DANIEL DREW
Insulation 1/7/2021 Not Ready for Inspection DANIEL DREW
Underground Mechanical 1/7/2021 Not Ready for Inspection DANIEL DREW
Insulation 1/11/2021 Partial Inspection DANIEL DREW
PLUMBING-Rough 1/11/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/14/2021 Partial Approval DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 2/3/2021 Not Ready for Inspection DANIEL DREW
ELECTRICAL-Rough 2/3/2021 Approved DANIEL DREW
Green Building Rough 2/3/2021 Not Ready for Inspection DANIEL DREW
HVAC-Rough 2/3/2021 Approved DANIEL DREW
PLUMBING-Rough 2/3/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 2/19/2021 Not Ready for Inspection DANIEL DREW
Green Building Rough 2/19/2021 Not Ready for Inspection DANIEL DREW
Insulation 2/23/2021 Approved DANIEL DREW
Interior/Exterior Lathing 2/23/2021 Approved DANIEL DREW
BUILDING-Rough-Frame 2/24/2021 Approved DANIEL DREW
Green Building Rough 2/24/2021 Approved DANIEL DREW
Insulation 2/24/2021 Approved DANIEL DREW
Interior/Exterior Lathing 2/24/2021 Approved DANIEL DREW
Wood Frame 2/24/2021 Approved DANIEL DREW
Drywall Nailing 3/2/2021 Approved DANIEL DREW
Interior/Exterior Lathing 3/2/2021 Approved DANIEL DREW
Shower Pan 3/2/2021 Approved DANIEL DREW
Final 4/15/2021 Corrections Issued DAVID MATSON
Green Building Final 4/15/2021 Not Ready for Inspection DAVID MATSON
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Approved DAVID MATSON
Service/Power Release 4/15/2021 Not Ready for Inspection DAVID MATSON
Smoke Detectors 4/15/2021 Approved DAVID MATSON
Final 4/30/2021 Not Ready for Inspection DANIEL DREW
Gas Test 4/30/2021 Approved DANIEL DREW
Green Building Final 4/30/2021 Approved DANIEL DREW
Final 5/10/2021 Corrections Issued JOHN HAYES
Service/Power Release 5/10/2021 Not Ready for Inspection JOHN HAYES
Final 5/14/2021 Corrections Issued DANIEL DREW
Final 6/8/2021 Corrections Issued MICHEL ABAJAN
Final 6/14/2021 OK to Issue CofO ARAM AVEDISIAN