19909 W BRYANT ST 91306
Certificate Information: 19909 W BRYANT ST 91306
- Application / Permit
- 20014-20000-04363
- Plan Check / Job No.
- B20VN13104
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ATTACHED PATIO COVER AND CONVERT (E) 20'-2" X 20'-2" ATTACHED GARAGE FOR (N) BEDROOM, BATHROOM & WIC. ADD 18' X 18' FOR (N) ATTACHED CARPORT TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/17/2021
- Issuing Office
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2020 | RAPHAEL ROSAS |
| Corrections Issued | 10/22/2020 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 1/6/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/3/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 3/1/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/12/2021 | APPLICANT |
| Issued | 4/17/2021 | APPLICANT |
| CofO in Progress | 7/20/2022 | JEFFREY PARD |
| Permit Finaled | 7/28/2022 | JOHN JANSON |
| CofO Issued | 7/28/2022 | JOHN JANSON |
| Permit Finaled | 7/28/2022 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/10/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/16/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/16/2021 | GUILLERMO PETRA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Truong,, Phong Lap; Lic. No.: C70784 | 20754 TIMBERLINE LN WALNUT, CA 91789 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/26/2022 | Approved | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2022 | Approved | JEFFREY PARD |
| PLUMBING-Rough | 2/24/2022 | No Access for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 3/2/2022 | Partial Approval | JEFFREY PARD |
| ELECTRICAL-Rough | 4/8/2022 | Not Ready for Inspection | JEFFREY PARD |
| PLUMBING-Rough | 4/8/2022 | Approved | JEFFREY PARD |
| Wood Frame | 4/8/2022 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 4/15/2022 | Corrections Issued | JEFFREY PARD |
| ELECTRICAL-Rough | 4/19/2022 | Approved | JEFFREY PARD |
| HVAC-Rough | 4/26/2022 | Approved | JEFFREY PARD |
| Insulation | 5/4/2022 | Approved | JEFFREY PARD |
| Wood Frame | 5/4/2022 | Approved | JEFFREY PARD |
| Wood Frame | 5/13/2022 | Approved | JEFFREY PARD |
| Drywall Nailing | 5/19/2022 | Approved | JEFFREY PARD |
| Shower Pan | 5/19/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 5/24/2022 | Partial Inspection | KRISTEN CAUSEY |
| Interior/Exterior Lathing | 5/24/2022 | Partial Inspection | KRISTEN CAUSEY |
| Drywall Nailing | 5/26/2022 | Approved | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 6/22/2022 | Approved | JEFFREY PARD |
| Final | 6/22/2022 | OK to Issue CofO | JEFFREY PARD |
| Green Building Final | 6/22/2022 | Approved | JEFFREY PARD |
| Green Building Rough | 6/22/2022 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 6/22/2022 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Approved | JEFFREY PARD |