19909 W BRYANT ST 91306

Certificate Information: 19909 W BRYANT ST 91306

Application / Permit
20014-20000-04363
Plan Check / Job No.
B20VN13104
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ATTACHED PATIO COVER AND CONVERT (E) 20'-2" X 20'-2" ATTACHED GARAGE FOR (N) BEDROOM, BATHROOM & WIC. ADD 18' X 18' FOR (N) ATTACHED CARPORT TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 4/17/2021
Issuing Office
Current Status
CofO Issued on 7/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2020 APPLICANT
Assigned to Plan Check Engineer 10/21/2020 RAPHAEL ROSAS
Corrections Issued 10/22/2020 RAPHAEL ROSAS
Applicant returned to address corrections 1/6/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/3/2021 RAPHAEL ROSAS
Plan Check Approved 3/1/2021 RAPHAEL ROSAS
Building Plans Picked Up 3/12/2021 APPLICANT
Issued 4/17/2021 APPLICANT
CofO in Progress 7/20/2022 JEFFREY PARD
Permit Finaled 7/28/2022 JOHN JANSON
CofO Issued 7/28/2022 JOHN JANSON
Permit Finaled 7/28/2022 JOHN JANSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/10/2021 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 2/16/2021 GUILLERMO PETRA
Sewer availability Cleared 2/16/2021 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Approved JEFFREY PARD
PLUMBING-Rough 2/24/2022 No Access for Inspection JEFFREY PARD
PLUMBING-Rough 3/2/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 4/8/2022 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 4/8/2022 Approved JEFFREY PARD
Wood Frame 4/8/2022 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 4/15/2022 Corrections Issued JEFFREY PARD
ELECTRICAL-Rough 4/19/2022 Approved JEFFREY PARD
HVAC-Rough 4/26/2022 Approved JEFFREY PARD
Insulation 5/4/2022 Approved JEFFREY PARD
Wood Frame 5/4/2022 Approved JEFFREY PARD
Wood Frame 5/13/2022 Approved JEFFREY PARD
Drywall Nailing 5/19/2022 Approved JEFFREY PARD
Shower Pan 5/19/2022 Approved JEFFREY PARD
Green Building Rough 5/24/2022 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 5/24/2022 Partial Inspection KRISTEN CAUSEY
Drywall Nailing 5/26/2022 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 6/22/2022 Approved JEFFREY PARD
Final 6/22/2022 OK to Issue CofO JEFFREY PARD
Green Building Final 6/22/2022 Approved JEFFREY PARD
Green Building Rough 6/22/2022 Approved JEFFREY PARD
Interior/Exterior Lathing 6/22/2022 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 6/22/2022 Approved JEFFREY PARD