5934 N SHOSHONE AVE 91316
Certificate Information: 5934 N SHOSHONE AVE 91316
- Application / Permit
- 20014-20000-04346
- Plan Check / Job No.
- B20VN13042
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18' X 18' (E) DETACHED CARPORT AND ADD 4'-8" X 16'-4" TO CREATE (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/10/2021
- Issuing Office
- Current Status
- Issued on 2/10/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/13/2020 | RAPHAEL ROSAS |
| Corrections Issued | 11/15/2020 | RAPHAEL ROSAS |
| Issued | 2/10/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/28/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 2/2/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/2/2021 | RIDWAN HARDY |
| ZI | Cleared | 2/10/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/12/2021 | Partial Inspection | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 3/24/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 3/24/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/24/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 4/16/2021 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Partial Approval | STEVEN BACK |
| Green Building Rough | 4/16/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 4/16/2021 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 4/16/2021 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 5/13/2021 | Partial Approval | STEVEN BACK |
| ELECTRICAL-Rough | 5/13/2021 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2021 | Approved | STEVEN BACK |
| Green Building Rough | 5/13/2021 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 5/13/2021 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/13/2021 | Approved | STEVEN BACK |
| Drywall Nailing | 5/24/2021 | Partial Approval | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/24/2021 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/10/2021 | Approved | STEVEN BACK |
| Green Building Rough | 6/10/2021 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/10/2021 | Approved | STEVEN BACK |
| Shower Pan | 6/10/2021 | Approved | STEVEN BACK |
| Underground Mechanical | 6/10/2021 | Approved | STEVEN BACK |
| Final | 11/3/2021 | Not Ready for Inspection | SEAN HAUPT |
| Green Building Final | 11/3/2021 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/3/2021 | SGSOV Not Ready | SEAN HAUPT |
| Smoke Detectors | 11/3/2021 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 11/12/2021 | Approved | SEAN HAUPT |
| Final | 11/12/2021 | Conditional Approval | SEAN HAUPT |
| Green Building Final | 11/12/2021 | Approved | SEAN HAUPT |
| HVAC-Final | 11/12/2021 | Approved | SEAN HAUPT |
| PLUMBING-Final | 11/12/2021 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 11/12/2021 | Approved | SEAN HAUPT |