7419 N GLORIA AVE 91406

Certificate Information: 7419 N GLORIA AVE 91406

Application / Permit
20014-20000-04345
Plan Check / Job No.
B20VN13036
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD NEW 14'-0" x 44'-4" TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
Issued on 2/9/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/30/2020 APPLICANT
Assigned to Plan Check Engineer 11/24/2020 SEAN SHAHMIRI
Corrections Issued 11/28/2020 SEAN SHAHMIRI
Quality Review Completed 11/30/2020 OMID HEDAYAT
Building Plans Picked Up 12/7/2020 APPLICANT
Plan Check Approved 1/31/2022 SEAN SHAHMIRI
Applicant returned to address corrections 2/1/2022 SEAN SHAHMIRI
Issued 2/9/2022 APPLICANT

Permit Application Clearance Information

Sewer availability Cleared 12/28/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/21/2022 JOSE DUARTE-DIAZ
Low Impact Development Cleared 1/21/2022 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/21/2022 JOSE DUARTE-DIAZ

Contact Information

Architect Hefner,, Charles David; Lic. No.: C23963 6320 VAN NUYS BOULEVARD #225      VAN NUYS, CA 91401
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/1/2023 Not Ready for Inspection RAUL OLAGI
Underground Mechanical 6/1/2023 Not Ready for Inspection RAUL OLAGI
Deputy Drilled-In Anchors 6/14/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 6/30/2023 No Access for Inspection RAUL OLAGI
Footing/Foundation/Slab 7/11/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 7/25/2023 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 8/14/2023 Approved RAUL OLAGI
Wood Frame 9/28/2023 Corrections Issued CHRISTOPHER ROJAS
Wood Frame 10/3/2023 Partial Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval RAUL OLAGI
Special/Order Compliance 11/27/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 12/8/2023 Not Ready for Inspection RAUL OLAGI
Green Building Rough 12/8/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 12/8/2023 Not Ready for Inspection RAUL OLAGI
Footing/Foundation/Slab 12/12/2023 Approved RAUL OLAGI
PLUMBING-Rough 12/15/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 1/3/2024 No Access for Inspection RAUL OLAGI
Deputy Wood Construction 1/19/2024 Conditional Approval ROBERT GOLD
Interior/Exterior Lathing 2/15/2024 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/22/2024 Partial Inspection RAUL OLAGI
BUILDING-Rough-Frame 3/5/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 3/5/2024 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Corrections Issued JOHN COLEMAN
Green Building Rough 3/5/2024 Approved JOHN COLEMAN
HVAC-Rough 3/5/2024 Approved JOHN COLEMAN
Insulation 3/15/2024 Partial Inspection RAUL OLAGI
BUILDING-Rough-Frame 3/18/2024 Corrections Issued RAUL OLAGI
Insulation 3/18/2024 Corrections Issued RAUL OLAGI
Deputy Wood Construction 3/20/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 3/29/2024 Approved RAUL OLAGI
Insulation 3/29/2024 Approved RAUL OLAGI
Drywall Nailing 4/2/2024 Approved MATTHEW NELSON
Shower Pan 5/24/2024 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 5/28/2024 Corrections Issued SALVADOR MARTINEZ
Shower Pan 5/28/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 5/30/2024 Not Ready for Inspection RAUL OLAGI
Interior/Exterior Lathing 6/3/2024 Approved SALVADOR MARTINEZ
Final 8/9/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 8/9/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 8/9/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 8/9/2024 Approved SALVADOR MARTINEZ
Final 5/19/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 5/19/2025 Approved JENNIFER RABUCHIN
Final 12/26/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Final 5/21/2026 No Access for Inspection MICHAEL CORTEZ
Final 6/2/2026 Corrections Issued MICHAEL CORTEZ