7419 N GLORIA AVE 91406
Certificate Information: 7419 N GLORIA AVE 91406
- Application / Permit
- 20014-20000-04345
- Plan Check / Job No.
- B20VN13036
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW 14'-0" x 44'-4" TO (E) SINGLE FAMILY DWELLING AND INTERIOR REMODEL
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- Issued on 2/9/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | SEAN SHAHMIRI |
| Corrections Issued | 11/28/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 11/30/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/7/2020 | APPLICANT |
| Plan Check Approved | 1/31/2022 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/1/2022 | SEAN SHAHMIRI |
| Issued | 2/9/2022 | APPLICANT |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2022 | JOSE DUARTE-DIAZ |
| Low Impact Development | Cleared | 1/21/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Architect | Hefner,, Charles David; Lic. No.: C23963 | 6320 VAN NUYS BOULEVARD #225 VAN NUYS, CA 91401 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/1/2023 | Not Ready for Inspection | RAUL OLAGI |
| Underground Mechanical | 6/1/2023 | Not Ready for Inspection | RAUL OLAGI |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/30/2023 | No Access for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 7/11/2023 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 7/25/2023 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 8/14/2023 | Approved | RAUL OLAGI |
| Wood Frame | 9/28/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 10/3/2023 | Partial Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Partial Approval | RAUL OLAGI |
| Special/Order Compliance | 11/27/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/8/2023 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 12/8/2023 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 12/8/2023 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 12/12/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 12/15/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 1/3/2024 | No Access for Inspection | RAUL OLAGI |
| Deputy Wood Construction | 1/19/2024 | Conditional Approval | ROBERT GOLD |
| Interior/Exterior Lathing | 2/15/2024 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/22/2024 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/5/2024 | Corrections Issued | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/5/2024 | Approved | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2024 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 3/5/2024 | Approved | JOHN COLEMAN |
| HVAC-Rough | 3/5/2024 | Approved | JOHN COLEMAN |
| Insulation | 3/15/2024 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| Insulation | 3/18/2024 | Corrections Issued | RAUL OLAGI |
| Deputy Wood Construction | 3/20/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/29/2024 | Approved | RAUL OLAGI |
| Insulation | 3/29/2024 | Approved | RAUL OLAGI |
| Drywall Nailing | 4/2/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 5/24/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Shower Pan | 5/28/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 5/30/2024 | Not Ready for Inspection | RAUL OLAGI |
| Interior/Exterior Lathing | 6/3/2024 | Approved | SALVADOR MARTINEZ |
| Final | 8/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 8/9/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 8/9/2024 | Approved | SALVADOR MARTINEZ |
| Final | 5/19/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 5/19/2025 | Approved | JENNIFER RABUCHIN |
| Final | 12/26/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 5/21/2026 | No Access for Inspection | MICHAEL CORTEZ |
| Final | 6/2/2026 | Corrections Issued | MICHAEL CORTEZ |