17360 W HAMLIN ST 91406
Certificate Information: 17360 W HAMLIN ST 91406
- Application / Permit
- 20014-20000-04335
- Plan Check / Job No.
- B20VN12532
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF MASTER BEDROOM (12'-1" X 16') & INTERIOR REMODEL TO (E) 1-STORY SFD
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/6/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 10/6/2020 | APPLICANT |
| Plan Check Approved | 3/11/2021 | NILOOFAR MEHRAIN |
| Issued | 4/12/2021 | APPLICANT |
| CofO in Progress | 12/15/2022 | SEAN HAUPT |
| CofO Issued | 1/13/2023 | JOHN JANSON |
| Permit Finaled | 1/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/1/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 2/1/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | GUILLERMO PETRA |
| ZI | Cleared | 3/8/2021 | DANG NGUYEN |
Contact Information
| Contractor | Ind Construction Llc; Lic. No.: 937833-B | 16430 VENTURA BLVD STE 208 ENCINO, CA 91436 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 6/8/2021 | Approved | STEVEN BACK |
| Insulation | 6/21/2021 | Partial Approval | STEVEN BACK |
| Wood Frame | 6/21/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2021 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2021 | Partial Approval | STEVEN BACK |
| Deputy Wood Construction | 7/20/2021 | Conditional Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 10/14/2021 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 10/14/2021 | Approved | SEAN HAUPT |
| Green Building Rough | 10/14/2021 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 10/14/2021 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 2/8/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 3/3/2022 | Conditional Approval | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2022 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 3/10/2022 | Approved | SEAN HAUPT |
| Insulation | 3/21/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 3/21/2022 | Approved | MORRIS JACKSON |
| Shower Pan | 3/21/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 3/25/2022 | Approved | SEAN HAUPT |
| Final | 12/7/2022 | Corrections Issued | SEAN HAUPT |
| Green Building Final | 12/7/2022 | Not Ready for Inspection | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Approved | SEAN HAUPT |
| Smoke Detectors | 12/7/2022 | Approved | SEAN HAUPT |
| Final | 12/14/2022 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 12/14/2022 | Approved | SEAN HAUPT |