530 S BENTLEY AVE 90049

Certificate Information: 530 S BENTLEY AVE 90049

Application / Permit
20014-20000-04328
Plan Check / Job No.
B20VN12988
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 46' X 10'3" IRREGULAR SHAPED ADDITION TO (E) SFD TO ENLARGE LIVING ROOM AND BEDROOM , NEW 24'3" X 20' ATTACHED TWO CAR GARAGE , INTERIOR REMODEL TO (E) SFD TO REMODEL (4) BEDROOMS , (3)BATHROOMS, CREATE (1) BATHROOM , REMODEL LIVING ROOM , DINING ROOM , KITCHEN , RELOCATE LAUNDRY , NEW POWDER ROOM , CREATE (1) NEW BEDROOM , DOORS AND WINDOWS CHANGEOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/6/2021
Issuing Office
Current Status
Issued on 1/6/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/2/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 RARES BODEA
Corrections Issued 10/12/2020 RARES BODEA
Building Plans Picked Up 10/15/2020 APPLICANT
Plan Check Approved 1/6/2021 RARES BODEA
Issued 1/6/2021 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 10/21/2020 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 10/27/2020 DINAH GARIN
Sewer availability Cleared 10/27/2020 DINAH GARIN
Low Impact Development Cleared 12/9/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/4/2021 ABDULLAH SADOZAI
Grading Pre-Inspection Cleared 1/5/2021 RARES BODEA

Contact Information

Contractor Owner-Builder       ,
Engineer Hajdari,, Genti; Lic. No.: C88031 140 S MENTOR AVE APT #207      PASADENA, CA 91106

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/13/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 1/13/2021 Not Ready for Inspection CARLOS MATAMOROS
METHANE-Barrier 1/13/2021 Approved CARLOS MATAMOROS
METHANE-Subgrade 1/13/2021 Approved CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/14/2021 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 1/20/2021 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 1/20/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 1/27/2021 Partial Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/4/2021 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 6/10/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 6/10/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Rough 6/10/2021 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 6/15/2021 Corrections Issued CARLOS MATAMOROS
HVAC-Rough 6/15/2021 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/27/2021 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 7/27/2021 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 7/27/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 7/27/2021 Approved CARLOS MATAMOROS
MERV13>=Rough 7/27/2021 Approved CARLOS MATAMOROS
METHANE-Rough 7/27/2021 Approved CARLOS MATAMOROS
PLUMBING-Rough 7/27/2021 Approved CARLOS MATAMOROS
Shower Pan 7/27/2021 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 8/2/2021 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 8/5/2021 Corrections Issued CARLOS MATAMOROS
Deputy Wood Construction 8/5/2021 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/5/2021 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 8/5/2021 Not Ready for Inspection CARLOS MATAMOROS
Pre-Inspection 8/5/2021 Partial Inspection KRISTEN CAUSEY
Special/Order Compliance 8/5/2021 Partial Inspection ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/31/2021 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 10/19/2021 Corrections Issued CARLOS MATAMOROS
Green Building Rough 10/19/2021 Not Ready for Inspection CARLOS MATAMOROS
Insulation 10/19/2021 Partial Approval CARLOS MATAMOROS
BUILDING-Rough-Frame 11/2/2021 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 11/2/2021 Approved CARLOS MATAMOROS
Green Building Rough 11/2/2021 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/15/2021 Corrections Issued STEPHANIE SWANSON
Insulation 11/23/2021 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/23/2021 Partial Approval RYAN SALAZAR
Drywall Nailing 12/3/2021 Approved BRENDAN LOONEY
ELECTRICAL-Final 5/9/2022 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 5/9/2022 Approved CARLOS MATAMOROS
HVAC-Final 5/9/2022 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 5/9/2022 Not Ready for Inspection CARLOS MATAMOROS
Service/Power Release 5/11/2022 Approved CARLOS MATAMOROS
Special/Order Compliance 5/18/2022 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
Final 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 6/10/2022 Approved CARLOS MATAMOROS
Green Building Final 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
MERV13>=Final 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 6/10/2022 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 6/10/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 6/13/2022 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 6/15/2022 Approved CARLOS MATAMOROS
PLUMBING-Final 6/17/2022 Approved CARLOS MATAMOROS