14346 W CHAMBERLAIN ST 91345
Certificate Information: 14346 W CHAMBERLAIN ST 91345
- Application / Permit
- 20014-20000-04324
- Plan Check / Job No.
- B20VN12979
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION ( 27' 6" X 28' 4" ) L-SHAPED TO FRONT OF (E) SFD FOR (2) BEDROOMS (2) BATHROOMS AND LIVING ROOM EXTENSION. INTERIOR REMODEL TO ADD (1) BATHROOM AT (E) BEDROOM. WORK PER ENGINEERING.
- Permit Issued
- Issued on 12/14/2023
- Issuing Office
- Current Status
- Issued on 12/14/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 10/8/2020 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/12/2021 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 6/4/2021 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 6/8/2021 | APPLICANT |
| Plan Check Approved | 12/14/2023 | ROSENDO MEDINA |
| Issued | 12/14/2023 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2021 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/24/2021 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 4/14/2022 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 4/15/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dorta,, Michael Rohrs; Lic. No.: C72538 | 2445 VIA SONOMA PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/16/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 12/16/2023 | Approved | SEAN HAUPT |
| METHANE-Barrier | 12/16/2023 | Approved | SEAN HAUPT |
| METHANE-Subgrade | 12/16/2023 | Approved | SEAN HAUPT |
| Pre-Inspection | 12/16/2023 | Not Ready for Inspection | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 9/3/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/4/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/4/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/16/2025 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 9/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/30/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/3/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 10/3/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 10/8/2025 | Approved | JENNIFER RABUCHIN |