6832 N COSTELLO AVE 91405

Certificate Information: 6832 N COSTELLO AVE 91405

Application / Permit
20014-20000-04311
Plan Check / Job No.
B20VN12938
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EXTEND (E) LIVING ROOM (8'-11" X 8') TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL; RE-FRAME (E) ROOF FROM VAULTED TO CALIFORNIA FRAMING
Permit Issued
Issued on 12/10/2020
Issuing Office
Current Status
CofO Issued on 4/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 NILOOFAR MEHRAIN
Corrections Issued 10/13/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 10/14/2020 APPLICANT
Issued 12/10/2020 APPLICANT
CofO in Progress 3/31/2022 RICHARD DOCKUS
Permit Finaled 4/4/2022 RONALD MYRICK
CofO Issued 4/4/2022 RONALD MYRICK
Permit Finaled 4/4/2022 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/28/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/29/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,
Engineer Truong,, Phong Lap; Lic. No.: C70784 20754 TIMBERLINE LN      WALNUT, CA 91789

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2021 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 9/27/2021 Approved RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 10/14/2021 Approved RICHARD DOCKUS
HVAC-Rough 10/14/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 10/14/2021 Approved RICHARD DOCKUS
Wood Frame 10/14/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 10/28/2021 Partial Approval ALAN MORELOS
Insulation 11/8/2021 Approved RICHARD DOCKUS
Drywall Nailing 11/15/2021 Approved ALAN MORELOS
BUILDING-Rough-Frame 3/11/2022 Not Ready for Inspection JOHN HAYES
Final 3/11/2022 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/11/2022 Not Ready for Inspection JOHN HAYES
Green Building Final 3/11/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/11/2022 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/11/2022 SGSOV Not Ready JOHN HAYES
Smoke Detectors 3/11/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 3/25/2022 Approved RICHARD DOCKUS
Final 3/25/2022 OK to Issue CofO RICHARD DOCKUS
Footing/Foundation/Slab 3/25/2022 Approved RICHARD DOCKUS
Green Building Final 3/25/2022 Approved RICHARD DOCKUS
Green Building Rough 3/25/2022 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 3/25/2022 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 3/25/2022 Approved RICHARD DOCKUS