9447 N VALJEAN AVE 91343

Certificate Information: 9447 N VALJEAN AVE 91343

Application / Permit
20014-20000-04300
Plan Check / Job No.
B20VN12888
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d) & EXTEND FOR (N) BEDROOM & BATHROOM (10'-4" X 20') PER WFPP
Permit Issued
Issued on 12/8/2020
Issuing Office
Current Status
CofO Issued on 8/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 NILOOFAR MEHRAIN
Corrections Issued 10/13/2020 NILOOFAR MEHRAIN
Building Plans Picked Up 10/14/2020 APPLICANT
Plan Check Approved 12/8/2020 NILOOFAR MEHRAIN
Issued 12/8/2020 APPLICANT
CofO in Progress 7/28/2022 ALAN MORELOS
Permit Finaled 8/22/2022 MICHAEL SMITH
CofO Issued 8/22/2022 MICHAEL SMITH
Permit Finaled 8/22/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 10/19/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/20/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/20/2020 JOHN TRIANTAFYLLOS
Grading Pre-Inspection Cleared 10/28/2020 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/28/2021 Partial Approval ARTHUR SARGSYAN
PLUMBING-Rough 5/28/2021 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/8/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 8/23/2021 Approved MICHAEL TEMPLE
PLUMBING-Rough 8/23/2021 Approved MICHAEL TEMPLE
Underground Mechanical 8/23/2021 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 10/18/2021 Approved RAUL OLAGI
Green Building Rough 10/18/2021 Approved RAUL OLAGI
HVAC-Rough 10/18/2021 Partial Approval RAUL OLAGI
Insulation 11/18/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 11/18/2021 Partial Approval RAUL OLAGI
Drywall Nailing 12/10/2021 Approved MICHAEL TEMPLE
Shower Pan 12/10/2021 Corrections Issued MICHAEL TEMPLE
Shower Pan 12/15/2021 Approved RAUL OLAGI
Interior/Exterior Lathing 1/12/2022 Approved RAUL OLAGI
Service/Power Release 4/15/2022 Corrections Issued RAUL OLAGI
Underground Mechanical 4/15/2022 Approved RAUL OLAGI
ELECTRICAL-Final 7/22/2022 Approved ALAN MORELOS
Final 7/22/2022 Corrections Issued ALAN MORELOS
Footing/Foundation/Slab 7/22/2022 Approved ALAN MORELOS
Green Building Final 7/22/2022 Not Ready for Inspection ALAN MORELOS
HVAC-Final 7/22/2022 Not Ready for Inspection ALAN MORELOS
PLUMBING-Final 7/22/2022 Corrections Issued ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 7/22/2022 SGSOV Approved ALAN MORELOS
Service/Power Release 7/22/2022 Not Ready for Inspection ALAN MORELOS
Smoke Detectors 7/22/2022 Approved ALAN MORELOS
ELECTRICAL-Final 7/27/2022 Approved ALAN MORELOS
Final 7/27/2022 OK to Issue CofO ALAN MORELOS
Green Building Final 7/27/2022 Approved ALAN MORELOS
HVAC-Final 7/27/2022 Approved ALAN MORELOS
PLUMBING-Final 7/27/2022 Approved ALAN MORELOS
Service/Power Release 7/27/2022 Approved ALAN MORELOS