3101 W COLISEUM ST 90018
Certificate Information: 3101 W COLISEUM ST 90018
- Application / Permit
- 20014-20000-04296
- Plan Check / Job No.
- B20VN12869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DEMO (E) BARBEQUE ROOM (15' X 20') & ADD (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (d) TO (E) GARAGE
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofO Issued on 6/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/13/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 10/15/2020 | APPLICANT |
| Plan Check Approved | 1/12/2021 | NILOOFAR MEHRAIN |
| Issued | 4/27/2021 | APPLICANT |
| CofO in Progress | 6/4/2024 | ANTHONY EGSON |
| Permit Finaled | 6/11/2024 | DEROLD HAUFF |
| Permit Finaled | 6/11/2024 | DEROLD HAUFF |
| CofO Issued | 6/11/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 10/20/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 11/18/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 1/6/2021 | MATTHEW CRAIG |
Contact Information
| Contractor | A1 Builders Inc; Lic. No.: 1031190-B | 16501 VENTURA BLVD STE 400 ENCINO, CA 91436 |
| Engineer | Boranian,, Paul Darian; Lic. No.: S5944 | 23261 BURBANK BL WOODLAND HILLS, CA 91367 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/3/2021 | Partial Approval | DAVID FEILER |
| Special/Order Compliance | 8/3/2021 | Corrections Issued | DAVID FEILER |
| Footing/Foundation/Slab | 8/31/2021 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 1/25/2022 | Corrections Issued | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/6/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/6/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 4/6/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 4/6/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/29/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/29/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/29/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/29/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/17/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | HORACE FULTZ |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | HORACE FULTZ |
| Sewer | 6/7/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 6/14/2022 | Partial Approval | HORACE FULTZ |
| ELECTRICAL-Final | 9/22/2022 | Approved | ANTHONY EGSON |
| Final | 9/22/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 9/22/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 9/22/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/22/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/22/2022 | Approved | ANTHONY EGSON |
| Final | 9/30/2022 | Conditional Approval | ANTHONY EGSON |
| Green Building Final | 9/30/2022 | Approved | ANTHONY EGSON |
| Final | 4/18/2023 | Corrections Issued | ANTHONY EGSON |
| Final | 6/4/2024 | OK to Issue CofO | ANTHONY EGSON |