7810 S BOEING AVE 90045
Certificate Information: 7810 S BOEING AVE 90045
- Application / Permit
- 20014-20000-04286
- Plan Check / Job No.
- B20VN12844
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXPAND (E) BATHROOM (7'-10" X 8'-5"), BEDROOM/BATHROOM/KITCHEN (IRR SHAPED, 151SF) & ADD PATIO COVER (5' X 30'-6") TO (E) 1-STORY SFD W/ ATTACHED GARAGE; INTERIOR REMODEL
- Permit Issued
- Issued on 12/17/2020
- Issuing Office
- Current Status
- CofO Issued on 6/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/4/2020 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 11/5/2020 | APPLICANT |
| Plan Check Approved | 12/3/2020 | NILOOFAR MEHRAIN |
| Issued | 12/17/2020 | APPLICANT |
| CofO in Progress | 5/25/2021 | BRENDAN LOONEY |
| CofO Issued | 6/10/2021 | VINCENT COTTON |
| Permit Finaled | 6/10/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/17/2020 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2020 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 11/24/2020 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 11/25/2020 | NIKTA MOUSAVI |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 1/7/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 1/22/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/22/2021 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 1/22/2021 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Approved | DAVID HEINE |
| HVAC-Rough | 2/22/2021 | Approved | DAVID HEINE |
| PLUMBING-Rough | 2/22/2021 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 2/26/2021 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 2/26/2021 | Approved | DAVID HEINE |
| Green Building Rough | 2/26/2021 | Not Ready for Inspection | DAVID HEINE |
| Shower Pan | 2/26/2021 | Approved | DAVID HEINE |
| Insulation | 3/9/2021 | Not Ready for Inspection | PIERRE VEGA |
| Interior/Exterior Lathing | 3/9/2021 | Partial Approval | PIERRE VEGA |
| BUILDING-Rough-Frame | 3/11/2021 | Approved | DAVID HEINE |
| Green Building Rough | 3/11/2021 | Approved | DAVID HEINE |
| Insulation | 3/11/2021 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 3/11/2021 | Approved | DAVID HEINE |
| Drywall Nailing | 3/16/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 3/16/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 5/18/2021 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 5/18/2021 | Approved | BRENDAN LOONEY |
| Gas Test | 5/18/2021 | Approved | BRENDAN LOONEY |
| Green Building Final | 5/18/2021 | Approved | BRENDAN LOONEY |
| HVAC-Final | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| PLUMBING-Final | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 5/18/2021 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Structural Steel Frame | 5/18/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| ELECTRICAL-Final | 5/24/2021 | Approved | BRENDAN LOONEY |
| Final | 5/24/2021 | OK to Issue CofO | BRENDAN LOONEY |
| HVAC-Final | 5/24/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 5/24/2021 | Approved | BRENDAN LOONEY |
| Service/Power Release | 5/24/2021 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 5/24/2021 | Approved | BRENDAN LOONEY |
| Structural Steel Frame | 5/24/2021 | Approved | BRENDAN LOONEY |