6224 N VAN NOORD AVE 91401

Certificate Information: 6224 N VAN NOORD AVE 91401

Application / Permit
20014-20000-04280
Plan Check / Job No.
B20VN12838
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR INTERIOR REMODEL TO (E) SFD TO REVISE ENTIRE FLOOR PLAN LAYOUT WITH 29' 8" X 33' 6" 2ND FLOOR ADDITION, 12' X 26' 6" TRELLIS ADDITION, 4' 3" X 11' 5" COVERD PORCH ADDITION AND REMOVE (E) FRONT COVERED PORCH. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 10/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 GURUNATH NESARAJAH
Corrections Issued 11/7/2020 GURUNATH NESARAJAH
Applicant returned to address corrections 5/26/2021 GURUNATH NESARAJAH
Building Plans Picked Up 5/26/2021 APPLICANT
Plan Check Approved 2/7/2022 GURUNATH NESARAJAH
Issued 2/14/2022 APPLICANT
CofO in Progress 9/27/2023 JUAN VALENZUELA
CofO Issued 10/23/2023 RUBEN SALAS
Permit Finaled 10/23/2023 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 8/25/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 8/26/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 12/2/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 12/7/2021 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/1/2022 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 4/7/2022 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval CHRISTOPHE COCHRAN
Pre-Inspection 4/14/2022 Approved CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/19/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/19/2022 Partial Approval CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/2/2022 No Access for Inspection CHRISTOPHE COCHRAN
Light Gage Steel Frame 5/2/2022 No Access for Inspection CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/2/2022 SGSOV Not Ready CHRISTOPHE COCHRAN
Wood Frame 5/2/2022 No Access for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 5/4/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 5/4/2022 Corrections Issued CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 5/5/2022 Conditional Approval MICHAEL TEMPLE
PLUMBING-Rough 5/6/2022 Corrections Issued CHRISTOPHE COCHRAN
Wood Frame 5/6/2022 Partial Approval CHRISTOPHE COCHRAN
PLUMBING-Rough 5/10/2022 Partial Approval CHRISTOPHE COCHRAN
Insulation 5/12/2022 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Approved RAFAEL CORTES
Pre-Inspection 8/4/2022 Approved RAFAEL CORTES
BUILDING-Rough-Frame 8/29/2022 Not Ready for Inspection RAFAEL CORTES
Green Building Rough 8/29/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Rough 8/29/2022 Corrections Issued RAFAEL CORTES
ELECTRICAL-Rough 9/28/2022 Not Ready for Inspection RAFAEL CORTES
HVAC-Rough 9/28/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 9/28/2022 Not Ready for Inspection RAFAEL CORTES
BUILDING-Rough-Frame 10/3/2022 Corrections Issued RAFAEL CORTES
ELECTRICAL-Rough 10/3/2022 Approved RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 10/3/2022 Approved RAFAEL CORTES
HVAC-Rough 10/3/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 10/11/2022 Not Ready for Inspection RAFAEL CORTES
Shower Pan 10/11/2022 Not Ready for Inspection RAFAEL CORTES
PLUMBING-Rough 10/17/2022 Approved WILLIAM WREN
Shower Pan 10/17/2022 Approved WILLIAM WREN
BUILDING-Rough-Frame 10/18/2022 Conditional Approval CALEB MEISTER
Green Building Rough 10/18/2022 Approved CALEB MEISTER
HVAC-Rough 10/18/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 10/18/2022 Approved CALEB MEISTER
Insulation 10/24/2022 Approved CALEB MEISTER
Verify Sprinkler Sign Off 10/25/2022 Corrections Issued CALEB MEISTER
Interior/Exterior Lathing 11/1/2022 Partial Approval JENNIFER RABUCHIN
Special/Order Compliance 11/1/2022 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 11/29/2022 Approved KIRK SANDERS
Drywall Nailing 12/29/2022 Partial Approval KIRK SANDERS
Drywall Nailing 1/6/2023 Approved KIRK SANDERS
ELECTRICAL-Final 3/22/2023 Not Ready for Inspection KIRK SANDERS
Pre-Inspection 7/5/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 8/23/2023 Approved KIRK SANDERS
Final 8/23/2023 Corrections Issued KIRK SANDERS
Green Building Final 8/23/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 8/23/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 8/23/2023 Approved KIRK SANDERS
Final 8/28/2023 Corrections Issued KIRK SANDERS
Final 9/11/2023 OK to Issue CofO JUAN VALENZUELA