3725 1/2 W TRACY ST 90027
Certificate Information: 3725 1/2 W TRACY ST 90027
- Application / Permit
- 20014-20000-04274
- Plan Check / Job No.
- B20VN12823
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD NEW 30'x40' ACCESSORY DWELLING UNIT ABOVE (E) DETACHED GARAGE PER LAMC 12.22 A.33 (c)-(d); TYPE V-A CONSTRUCTION; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
- Permit Issued
- Issued on 5/11/2022
- Issuing Office
- Current Status
- CofO Issued on 7/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2020 | SEAN SHAHMIRI |
| Corrections Issued | 10/26/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 12/1/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 12/2/2020 | APPLICANT |
| Applicant returned to address corrections | 8/31/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 11/4/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 2/10/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 5/9/2022 | SEAN SHAHMIRI |
| Issued | 5/11/2022 | APPLICANT |
| CofO in Progress | 6/30/2023 | JOSEPH MCGARRY |
| Permit Finaled | 7/13/2023 | DEROLD HAUFF |
| CofO Issued | 7/13/2023 | DEROLD HAUFF |
| Permit Finaled | 7/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2020 | CECILIO NAVARRO |
| Street Frontage | Cleared | 12/8/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/23/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/23/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 6/23/2021 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 7/14/2021 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 7/28/2021 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 8/31/2021 | SEAN SHAHMIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/7/2022 | Partial Approval | JOSEPH MCGARRY |
| Pre-Inspection | 9/20/2022 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 9/20/2022 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 9/26/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Rough | 9/26/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Reinforced Concrete Frame | 9/26/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 9/26/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 9/27/2022 | Partial Approval | JOSEPH MCGARRY |
| Special/Order Compliance | 9/28/2022 | Partial Inspection | JOSEPH MCGARRY |
| Special/Order Compliance | 9/30/2022 | Approved | JOSEPH MCGARRY |
| Underground Mechanical | 10/3/2022 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Gas Test | 10/4/2022 | Partial Approval | JOSEPH MCGARRY |
| Sewer | 10/4/2022 | Approved | JOSEPH MCGARRY |
| Deputy Steel/Welding | 10/12/2022 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/13/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 11/7/2022 | No Access for Inspection | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 11/10/2022 | Partial Approval | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Wood Frame | 11/22/2022 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Corrections Issued | JOSEPH MCGARRY |
| Wood Frame | 12/21/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 12/28/2022 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/18/2023 | Corrections Issued | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 1/18/2023 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 1/18/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 1/18/2023 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 1/18/2023 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 1/18/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/26/2023 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 1/26/2023 | Approved | JOSEPH MCGARRY |
| Insulation | 2/3/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/3/2023 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 2/7/2023 | Approved | RICHARD DOCKUS |
| Final | 5/17/2023 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/17/2023 | Approved | JOSEPH MCGARRY |
| Green Building Final | 5/17/2023 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 5/17/2023 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 5/17/2023 | Approved | JOSEPH MCGARRY |
| Final | 5/24/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 6/28/2023 | OK to Issue CofO | JOSEPH MCGARRY |