20455 W PLUMMER ST 91311

Certificate Information: 20455 W PLUMMER ST 91311

Application / Permit
20014-20000-04266
Plan Check / Job No.
B20VN12790
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DEMO EX ATT PATIO COVER AND CONVERT EX DET GARAGE INTO ACCESSORY DWELLING UNIT PER ORD #186,481 WITH 10'5"X20'2"ADDITION. ALL WORK PER WFPP.
Permit Issued
Issued on 6/14/2021
Issuing Office
Current Status
CofO Issued on 12/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2020 APPLICANT
Assigned to Plan Check Engineer 10/29/2020 HAYATO TSUCHIYA
Corrections Issued 10/31/2020 HAYATO TSUCHIYA
Plan Check Approved 3/20/2021 HAYATO TSUCHIYA
Building Plans Picked Up 3/22/2021 APPLICANT
Issued 6/14/2021 APPLICANT
CofO in Progress 12/16/2024 DAVID SCANTLIN
Permit Finaled 12/16/2024 JOHN JANSON
CofO Issued 12/16/2024 JOHN JANSON
Permit Finaled 12/16/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/17/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 2/17/2021 ADRIAN CASTRO
Sewer availability Cleared 2/17/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 3/11/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/9/2021 Approved JEFFREY PARD
Gas Test 5/2/2022 Approved JEFFREY PARD
PLUMBING-Rough 5/2/2022 Partial Approval JEFFREY PARD
Sewer 5/2/2022 Approved JEFFREY PARD
Underground Mechanical 5/2/2022 Approved JEFFREY PARD
Deputy Drilled-In Anchors 6/23/2022 Approved JEFFREY PARD
Footing/Foundation/Slab 7/5/2022 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/4/2022 Approved JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Approved JEFFREY PARD
Gas Test 8/4/2022 Approved JEFFREY PARD
PLUMBING-Rough 8/4/2022 Approved JEFFREY PARD
Wood Frame 8/4/2022 Partial Approval JEFFREY PARD
HVAC-Rough 6/12/2024 Approved DAVID SCANTLIN
Wood Frame 6/12/2024 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 8/1/2024 Approved DAVID SCANTLIN
Green Building Rough 8/1/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/1/2024 Partial Approval DAVID SCANTLIN
Insulation 8/23/2024 Approved DAVID SCANTLIN
Drywall Nailing 9/17/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 9/17/2024 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 10/1/2024 Approved DAVID SCANTLIN
Final 12/2/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 12/2/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/2/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 12/2/2024 Approved DAVID SCANTLIN
Final 12/16/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 12/16/2024 Approved DAVID SCANTLIN
Service/Power Release 12/16/2024 Approved DAVID SCANTLIN