15025 W VALLEYHEART DR 91403

Certificate Information: 15025 W VALLEYHEART DR 91403

Application / Permit
20014-20000-04263
Plan Check / Job No.
B20VN12787
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL, 12' X 4' AND 10'-9 X 4' FIRST ADDITION IN REAR AND 6'-2" X 5' FIRST AND SECOND STORY ADDITION TO (E) SINGLE FAMILY DWELLING WITH ATT. GARAGE. ALL WORK PER ENGINEERING. NFPA 13D REQUIRED THROUGHOUT
Permit Issued
Issued on 3/2/2021
Issuing Office
Current Status
CofO Issued on 1/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/30/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 11/18/2020 OMID HEDAYAT
Building Plans Picked Up 11/18/2020 APPLICANT
Plan Check Approved 2/25/2021 SEWADA ZADOORAN MILAGARDI
Issued 3/2/2021 APPLICANT
CofO in Progress 12/8/2021 JACK KARGODORIAN
CofO Issued 1/26/2022 MICHAEL SMITH
Permit Finaled 1/26/2022 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 12/1/2020 DANG NGUYEN
Roof/Waste drainage to street Cleared 12/3/2020 GUILLERMO PETRA
Sewer availability Cleared 12/3/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/4/2020 GUILLERMO PETRA
ZI Cleared 12/21/2020 MIGUEL GAMBOA

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21500 WYANDOTTE ST 106      CANOGA PARK, CA 91303

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/10/2021 Corrections Issued BEAU COLLINS
PLUMBING-Rough 3/10/2021 Partial Approval BEAU COLLINS
Excavation/Setback/Form/Re-Bar 3/12/2021 Approved CHARLES POWELL
ELECTRICAL-Rough 5/5/2021 Approved CHARLES POWELL
PLUMBING-Rough 5/5/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 5/10/2021 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Approved CHARLES POWELL
Green Building Rough 5/10/2021 Not Ready for Inspection CHARLES POWELL
HVAC-Rough 5/10/2021 Approved CHARLES POWELL
MERV13>=Rough 5/10/2021 Approved CHARLES POWELL
Insulation 5/17/2021 Approved CHARLES POWELL
Interior/Exterior Lathing 5/17/2021 Partial Approval CHARLES POWELL
Shower Pan 5/17/2021 Approved CHARLES POWELL
Drywall Nailing 5/27/2021 Not Ready for Inspection JUSTIN HAWLEY
Green Building Rough 5/27/2021 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 5/27/2021 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 6/3/2021 Corrections Issued HENRY KIM
Drywall Nailing 6/3/2021 Partial Approval HENRY KIM
Verify Sprinkler Sign Off 6/3/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/30/2021 SGSOV Not Ready MISAEL ESPARZA
BUILDING-Rough-Frame 10/14/2021 Approved JACK KARGODORIAN
Drywall Nailing 10/14/2021 Approved JACK KARGODORIAN
Final 10/14/2021 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 10/14/2021 Partial Inspection JACK KARGODORIAN
Green Building Final 10/14/2021 Not Ready for Inspection JACK KARGODORIAN
MERV13>=Final 10/14/2021 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 10/14/2021 Approved JACK KARGODORIAN
Final 11/23/2021 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 11/23/2021 Approved MATT KELLERMAN
Green Building Final 11/23/2021 Approved MATT KELLERMAN
Final 12/2/2021 Conditional Approval JACK KARGODORIAN
Final 12/8/2021 OK to Issue CofO JACK KARGODORIAN