7320-7320 1/2 S 9TH AVE 90043

Certificate Information: 7320-7320 1/2 S 9TH AVE 90043

Application / Permit
20014-20000-04250
Plan Check / Job No.
B20VN12754
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
MAJOR REMODEL & ADDITION TO (E) SFD AND CONVERT TO DUPLEX (55'-11"x30'-2") FIRE SPRINKLERED NFPA-13D
Permit Issued
Issued on 3/16/2021
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/22/2020 MOHAMMAD ESMAILI
Corrections Issued 10/24/2020 MOHAMMAD ESMAILI
Quality Review Completed 10/30/2020 OMID HEDAYAT
Building Plans Picked Up 10/30/2020 APPLICANT
Plan Check Approved 2/26/2021 MOHAMMAD ESMAILI
Issued 3/16/2021 APPLICANT
CofO in Progress 12/8/2021 FREDDIE RIVERA
Permit Finaled 12/17/2021 DEROLD HAUFF
CofO Issued 12/17/2021 DEROLD HAUFF
Permit Finaled 12/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/4/2020 CECILIO NAVARRO
Highway dedication Cleared 11/4/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 11/5/2020 CECILIO NAVARRO
Sewer availability Cleared 11/5/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 12/4/2020 CECILIO NAVARRO
Frnt yard landscape/Water mgmt Cleared 1/11/2021 MIGUEL GAMBOA
Tenant Habitability Plan Cleared 1/25/2021 MICHAEL SOTO

Contact Information

Contractor Trade Construction Services Inc; Lic. No.: 1062967-B 18717 PARTHENIA STREET #10      NORTHRIDGE, CA 91324
Engineer Lee,, Richard C C; Lic. No.: S1371 19558 GAULT ST      RESEDA, CA 91335

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/5/2021 Corrections Issued EUGENE CASSIDY
Pre-Inspection 4/5/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 4/6/2021 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/9/2021 Partial Approval FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 4/27/2021 Approved FREDDIE RIVERA
Pre-Inspection 4/27/2021 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 5/13/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 6/10/2021 Approved FREDDIE RIVERA
HVAC-Rough 6/10/2021 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 6/10/2021 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 6/18/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/24/2021 Approved HORACE FULTZ
Green Building Rough 6/24/2021 Approved HORACE FULTZ
Insulation 6/29/2021 Approved HORACE FULTZ
Drywall Nailing 7/1/2021 Approved RUBEN SALAS
Interior/Exterior Lathing 7/1/2021 Approved RUBEN SALAS
ELECTRICAL-Final 9/16/2021 Not Ready for Inspection FREDDIE RIVERA
HVAC-Final 9/16/2021 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Final 9/16/2021 Corrections Issued FREDDIE RIVERA
Verify Rec and Parks Fee Memo 9/16/2021 Approved FREDDIE RIVERA
ELECTRICAL-Final 9/24/2021 Approved FREDDIE RIVERA
HVAC-Final 9/24/2021 Approved FREDDIE RIVERA
PLUMBING-Final 9/24/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 11/19/2021 Not Ready for Inspection DANIEL GONZALEZ
Final 11/24/2021 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 11/24/2021 Approved FREDDIE RIVERA
Green Building Final 11/24/2021 Approved FREDDIE RIVERA
Service/Power Release 11/24/2021 Approved FREDDIE RIVERA
Smoke Detectors 11/24/2021 Approved FREDDIE RIVERA